Project would replace the existing culinary water collection & transmission system in Maple Canyon to replace existing system. Project would temporarily affect Mapleton roadless area via overland equipment and truck access.
Location
Maple Canyon. Waterline runs from storage tank near the mouth of Maple canyon approx. 2 miles up canyon, with three forks in the system up sub canyons.
Project timeline
1
Scoping Start
07/06/2023
2
Decision
08/2023 (Estimated)
3
Implementation
08/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Facility Maintenance |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Spanish Fork Ranger District |
| Legal Land Description | Not Applicable |