Project would construct a new access road affecting up to 0.6 acres to two culinary water storage reservoirs and would restore the existing 1.6acre access road. Access to existing ROW will be blocked by future development.
Location
East bench above Lindon City, an area known as the Canberra neighborhood.
Project timeline
1
Scoping Start
10/02/2023
2
Decision
10/2023 (Estimated)
3
Implementation
10/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Lindon City Reservoir Access Road Relocation | Decision Signed Date: 10/11/2023 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Pleasant Grove Ranger District |
| Legal Land Description | Not Applicable |