UDOT proposes to compete rockfall/hazard mitigation on 1-acre of federal land adjacent to SR158 in response to safety concerns.
Location
Road/dam cut on State Route (SR) 158, immediately north of Pineview Dam, between mileposts 0.1 and 0.5.
Project timeline
1
Scoping Start
03/03/2025
2
Decision
03/2025 (Estimated)
3
Implementation
04/2025 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| UDOT SR158 Rockfall Mitigation | Decision Signed Date: 03/14/2025 |
| Forests | Uinta-Wasatch-Cache National Forest |
| Districts | Ogden Ranger District |
| Legal Land Description | Not Applicable |