Renewal of Sprint Communications Company L.P. Right of Way Permit for 10 years for a buried fiber optic cable that runs through the Soledad Canyon area along the Southern Pacific Railroad tracks. ROW is 6,055' long and and 10' wide, 1.39 ac
Location
Buried cable runs along Southern Pacific Railroad tracks in Soledad Canyon
Project timeline
1
Scoping Start
02/25/2013
2
Comment Period
02/25/2013
3
Decision
12/2013 (Estimated)
4
Implementation
02/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (10) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Decision Memo for Sprint Communications Co, L.P. Fiber Optic Line Permit | Decision Signed Date: 12/16/2013 Legal Notice Date: 01/17/2014 |
| Forests | Angeles National Forest |
| Districts | Santa Clara/Mojave Rivers |
| Legal Land Description | Project begins on FS land at T4N, R14W, Sec 15 and ends at T4N, R14W, Sec 11 |