The project consists of pruning lower branches, removing competing brush, opening canopy cover, clearing a perimeter fuelbreak, and replanting trees at six forestry plantations.
Location
The six plantations are primarily located along Liebre Mountain Ridge between the Old Ridge Route on the west and Lake Hughes on the east.
Project timeline
1
Scoping Start
11/17/2011
2
Decision
06/2014 (Estimated)
3
Implementation
07/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | National Fire Plan - Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green); Watershed Improvements |
| SCMRRD Sawmill Liebre Integrated Forest Health Project | Decision Signed Date: 06/04/2014 |
| Forests | Angeles National Forest |
| Districts | Santa Clara/Mojave Rivers |
| Legal Land Description | Not Applicable |