Proposal is to implement Federal Aviation Administration (FAA) recommendations on an already approved transmission line. On National Forest System lands, marker balls would be added to 111 wire spans, and aviation lights to 3 towers.
Location
Two utility corridors south of Acton, CA. One southwest toward the Gould Substation off of Highway 2 in La Canada; the other southeast toward Duarte and the Rio Hondo Substation.
Project timeline
1
NOI in Federal Register
04/11/2013
2
DEIS NOA in Federal Register
04/19/2013
3
FEIS NOA in Federal Register
10/25/2013
4
Objection Period Start
06/13/2014
5
Decision
10/2014 (Estimated)
6
Implementation
03/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Electric Transmission |
| Tehachapi Renewable Transmission Project Supplemental EIS | Decision Signed Date: 10/17/2014 |
| Forests | Angeles National Forest |
| Districts | Angeles National Forest All Units |
| Legal Land Description | Not Applicable |