Permit seeker proposes to construct a new 120 feet communication tower to upgrade and replace an existing tower and add cement pads to accommodate the future pre-fabricated equipment buildings and additional tenants utilizing the site.
Location
T 3 N, R 8 W, NW 1/4 Section 13
Project timeline
1
Scoping Start
11/19/2018
2
Decision
03/2021 (Estimated)
3
Implementation
04/2021 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Blue Ridge Communication Site Inc. Tower Replacement | Decision Signed Date: 03/05/2021 |
| Forests | Angeles National Forest |
| Districts | San Gabriel River Ranger District |
| Legal Land Description | Not Applicable |