Permit seeker requested NFS SUP authorization for the continued occupancy and use of the existing well and associated domestic water infrastructure for rebuilding home following a catastrophic wildfire, pending appropriate LA county building permit.
Location
T 3 N, R 14 W, SE 1/4 , NW 1/4, Section 29
Project timeline
1
Scoping Start
11/19/2018
2
Decision
12/2018 (Estimated)
3
Implementation
03/2019 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Well, Water Tank and Water Line Permit Renewal | Decision Signed Date: 12/21/2018 |
| Forests | Angeles National Forest |
| Districts | Los Angeles River |
| Legal Land Description | Not Applicable |