The Cleveland NF proposes to allow SDG&E to construct powerline across portions of the national forest between Imperial Valley and San Diego.
Location
Various locations across the Descanso Ranger District
Project timeline
1
NOI in Federal Register
08/31/2006
2
DEIS NOA in Federal Register
01/11/2008
3
FEIS NOA in Federal Register
10/17/2008
4
Decision
07/2010 (Estimated)
5
Implementation
12/2010 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Plan Amendment; Noxious Weed Treatments; Road Maintenance; Road Improvements/Construction |
| San Diego Gas & Electric Special Use Authorization for the Sunrise Powerlin | Decision Signed Date: 07/09/2010 Legal Notice Date: 07/14/2010 |
| Forests | Cleveland National Forest |
| Districts | Descanso Ranger District |
| Legal Land Description | Not Applicable |