The project involves the reinforcement of the 80' radio tower foundation that would add a concrete matt slab, reinforcement of the legs and cross bracings, and increasing the height of the tower by 20 feet.
Location
Monument Peak communications site on Mount Laguna
Project timeline
1
Scoping Start
03/21/2016
2
Decision
04/2016 (Estimated)
3
Implementation
05/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Monument Peak County Radio Tower Modification | Decision Signed Date: 04/28/2016 |
| Forests | Cleveland National Forest |
| Districts | Descanso Ranger District |
| Legal Land Description | Township 15 S, Range 5 East, Section 1 along the San Bernardino Meridian |