Approve construction of improvements needed to operate a generator in Santiago Peak, Building 10. Improvements include a concrete pad with walls, under 50 feet of buried propane line, fence relocation and building modifications.
Location
On top of Santiago Peak, along North Main Divide Road on the Trabuco Ranger District.
Project timeline
1
Scoping Start
08/28/2017
2
Decision
01/2018 (Estimated)
3
Implementation
04/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Santiago Peak Communications Facility 10 Generator Project | Decision Signed Date: 01/19/2018 |
| Forests | Cleveland National Forest |
| Districts | Trabuco Ranger District |
| Legal Land Description | T5S, R6W, S29 |