Changes to ongoing treatment program's 2013 EA - new areas to be treated, areas identified for reforestation, use of herbicide to prolong effectiveness of fuel breaks, and conduct limited treatment in recommended wilderness.
Location
Multiple locations on Palomar Mountain
Project timeline
1
Scoping Start
03/27/2019
2
Comment Period
11/19/2019
3
Objection Period Start
04/12/2020
4
Decision
06/2020 (Estimated)
5
Implementation
06/2020 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| Palomar Mountain Vegetation Treatment Program (Supplemental EA) | Decision Signed Date: 06/16/2020 |
| Forests | Cleveland National Forest |
| Districts | Palomar Ranger District |
| Legal Land Description | Not Applicable |