Construction of no more than a 0.75 mile of road, to replace the current Holiday Campground entrance road, which is at risk of destabilization due to run-off from the Birch Fire burn area. The current road will be decommissioned and rehabilitated.
Location
The proposed project area is about 400 m north of the existing campground entrance. New campground entrance road will connect Rock Creek Road (4S12) to the closest portion of the interior campground
Project timeline
1
Scoping Start
01/22/2013
2
Comment Period
07/23/2013
3
Decision
09/2013 (Estimated)
4
Implementation
05/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Developed Site Management; Road Improvements/Construction |
| Holiday Campground Entrance Road Project | Decision Signed Date: 09/20/2013 Legal Notice Date: 09/26/2013 |
| Forests | Inyo National Forest |
| Districts | White Mountain Ranger District |
| Legal Land Description | The project is located in the Tom's Place Quad, in the south half of T4S, R30E, Section 33. |