Decision Memo Completed

Oak Creek Mudflow Oak Tree Restoration Study

Inyo National Forest Inyo, California Mount Whitney Ranger District

This project proposes to plant oak seedlings in plots in the Oak Creek watershed on the mudflow to determine feasibility of oak restoration on the mud flow.

Location

On the Oak Creek mudflow

Project timeline

1
Scoping Start
11/10/2014
2
Decision
12/2014 (Estimated)
3
Implementation
12/2014 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (5), 36 Cfr 220.6(E)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements; Research And Development
Oak Creek Mudflow - Oak Restoration StudyDecision Signed Date: 12/05/2014
ForestsInyo National Forest
DistrictsMount Whitney Ranger District
Legal Land DescriptionT. 13S. R. 34 E. SEC. 3
ResearchVegetation management (other than forest products)