Verizon of CA is proposing to place a new 48 fiber optic line. The purpose of this project is to provide enhanced services and speeds for residents and travelers along 395 from the cell providers. The cable would be placed on existing DWP/SCE poles.
Location
The cable would be placed both area on DWP and SCE poles and directly buried with 2-1.25 inner ducts for approximately two miles from Toms Place to Sherwin Summit.
Project timeline
1
Scoping Start
11/28/2014
2
Decision
03/2015 (Estimated)
3
Implementation
04/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Verizon Wireless Fiber Optic Cable Project and Permit Amendment | Decision Signed Date: 03/12/2015 |
| Forests | Inyo National Forest |
| Districts | White Mountain Ranger District |
| Legal Land Description | TOMS PLACE, TOWNSHIP 5S, RANGE 30E, SECTIONS 1, 35, AND 34. |