Decision Memo Completed

Lee Vining spring water diversion and water pipeline permit reissuance

Inyo National Forest Mono, California Inyo National Forest All Units

Permit reissuance for water transmission pipeline and a spring diversion works to Lee Vining PUD, in Lee Vining Canyon. The water supply is about 5,357 feet long, and is underground. Eight foot right-of-way.

Location

Lee Vining Canyon

Project timeline

1
Scoping Start
10/11/2019
2
Decision
10/2020 (Estimated)
3
Implementation
10/2020 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Lee Vining spring water diversion and water pipeline permit reissuanceDecision Signed Date: 10/21/2020
ForestsInyo National Forest
DistrictsMono Ranger District
Legal Land DescriptionT1N, R26E, Sec. 17 & 19, and T1N, R25E, Sec 24
Special use management