Installation of two monitoring wells at the Hot Creek Fish Hatchery, to monitor groundwater quality effects from sewage percolation ponds.
Location
East and South of the Hot Creek Fish Hatchery, just outside of the private land boundary.
Project timeline
1
Scoping Start
06/02/2023
2
Decision
08/2023 (Estimated)
3
Implementation
08/2023 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Hot Creek Hatchery Groundwater Monitoring Wells | Decision Signed Date: 08/15/2023 |
| Forests | Inyo National Forest |
| Districts | Mammoth Ranger District |