Vegetation and fuels treatment in urban defense zones.Treatments may include thinning of live trees and brush, chipping, mastication, pilling and prescribed burning.
Location
Emerald Bay to Stateline Nevada
Project timeline
1
NOI in Federal Register
01/16/2008
2
DEIS NOA in Federal Register
05/10/2009
3
FEIS NOA in Federal Register
09/27/2011
4
Objection Period Start
09/28/2011
5
Decision
01/2012 (Estimated)
6
Implementation
08/2015 (Estimated)
NEPA / regulatory detail
| Special Authority | Hfra Title I: Wildland-Urban Interface |
| Notice and Comment Regulation | 218 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements |
| South Shore Fuel Reduction and Healthy Forest Restoration Project | Decision Signed Date: 01/10/2012 |
| Forests | Lake Tahoe Basin Mgt Unit |
| Districts | Lake Tahoe Basin Mgt Unit |