This project consists of approximately 3.9 miles of Class 1 or better trail linking Sierra Tract with Van Sickle Bi-State Park. Approximately .26 miles are on National Forest System land.
Location
The trail is proposed to go from Sierra Tract to Van Sickle Bi-State Park through the City of South Lake Tahoe.
Project timeline
1
Scoping Start
06/01/2011
2
Comment Period
06/01/2011
3
Decision
03/2012 (Estimated)
4
Implementation
05/2012 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations; Trail Management |
| Revised South Tahoe Greenway Shared Use Trail Project | Decision Signed Date: 03/01/2012 Legal Notice Date: 03/07/2012 |
| Forests | Lake Tahoe Basin Mgt Unit |
| Districts | Lake Tahoe Basin Mgt Unit |