Restore natural drainage patterns by breaching a ditch berm in 2-3 locations within a reach of approximately 70 feet and constructing 3-5 waterbars on an abandoned logging road on a terrace above Ward Creek near the Stanford Rock Road crossing.
Location
The Ward Creek Watershed
Project timeline
1
Scoping Start
06/30/2009
2
Decision
09/2009 (Estimated)
3
Implementation
08/2009 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (7), 36 Cfr 220.6(E)(7) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Watershed Improvements |
| Implementation of the Ward Creek Watershed Ecosystem Restoration Project | Decision Signed Date: 09/01/2009 |
| Forests | Lake Tahoe Basin Mgt Unit |
| Districts | Lake Tahoe Basin Mgt Unit |
| Legal Land Description | NW ? Section 23 of the Tahoe City, California Quadrangle map |