Protect long-term water quality of Lake Tahoe by reducing existing sediment source near the Valhalla Pier and provide access to the pier consistent with Forest Service Outdoor Recreation Accessibility Guidelines (FSORAG).
Location
The pier lies adjacent to Valhalla Hall and Boathouse Theater within the Tallac Historic Site.
Project timeline
1
Scoping Start
05/01/2009
2
Decision
06/2009 (Estimated)
3
Implementation
07/2009 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.12 (5), 36 Cfr 220.6(D)(5) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction; Watershed Improvements |
| Valhalla Pier Erosion Control and Accessibility Retrofit | Decision Signed Date: 06/25/2009 |
| Forests | Lake Tahoe Basin Mgt Unit |
| Districts | Lake Tahoe Basin Mgt Unit |
| Legal Land Description | Not Applicable |