Decision Memo Completed

Upper Bijou Park Creek Restoration and Water Quality Improvement Project

Lake Tahoe Basin Management Unit El Dorado, California Lake Tahoe Basin Mgt Unit

Project will construct erosion control improvements in the urban area of the Upper Bijou Park Creek, addressing flooding issues and needed roadway improvements. Creek channel will also be restored upstream and downstream of Pioneer Trail

Location

South Lake Tahoe, CA

Project timeline

1
Scoping Start
11/30/2022
2
Decision
04/2025 (Estimated)
3
Implementation
07/2025 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (25), 36 Cfr 220.6(E)(25)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
Upper Bijou Park Creek Restoration and Water Quality Improvement ProjectDecision Signed Date: 04/23/2025
ForestsLake Tahoe Basin Mgt Unit
DistrictsLake Tahoe Basin Mgt Unit
Legal Land DescriptionNot Applicable
Watershed management