Project timeline
1
Scoping Start
12/2023 (Estimated)
2
Comment Period
12/2023 (Estimated)
3
Objection Period Start
01/2024 (Estimated)
4
Decision
02/2024 (Estimated)
5
Implementation
05/2024 (Estimated)