To greatly reduce risk of line failure and for safer operations, Seneca has requested authorization to relocate select lines along existing roads and relocate old swing tanks to a centralized treating facility with newer & safer tanks.
Location
Sespe Oil Field, 5 miles north of Fillmore, CA.
Project timeline
1
Scoping Start
07/16/2012
2
Decision
03/2014 (Estimated)
3
Implementation
04/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Minerals Or Geology Plans Of Operations |
| Decision Memo - Seneca 2012 pipeline Relocation Project | Decision Signed Date: 03/24/2014 |
| Forests | Los Padres National Forest |
| Districts | Ojai Ranger District |
| Legal Land Description | Sections 28, 29, 31, 32 & 33, T5N, R19W, SBM |