Issuance of three new special use permits for a new term to replace three expired special use permits with only administrative changes. There are no changes to the authorized facilities or increase in the scope or intensity of activities.
Location
The project is located 5 miles north of Fillmore in the Sespe oil field.
Project timeline
1
Scoping Start
11/21/2013
2
Decision
03/2020 (Estimated)
3
Implementation
03/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Seneca Pipeline Special Use Permits Renewal | Decision Signed Date: 03/16/2020 |
| Forests | Los Padres National Forest |
| Districts | Ojai Ranger District |
| Legal Land Description | Sections 29, 30, 31, 32 & 33, T.5 N., R. 19 W., SBM |