SBA Towers proposes to reinforce the foundation of their existing authorized tower at the communication site at Cuesta Peak. 4 pieces of concrete will be installed between the 4 legs of the existing tower, and diagonal braces installed in 4 places.
Location
Approximately 6 miles SW of Santa Margarita, CA.
Project timeline
1
Scoping Start
09/21/2015
2
Decision
11/2015 (Estimated)
3
Implementation
09/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| SBA Tower Reinforcement Special Use Authorization Amendment | Decision Signed Date: 11/10/2015 |
| Forests | Los Padres National Forest |
| Districts | Santa Lucia Ranger District |
| Legal Land Description | T29S, R12E, Sec. 35, MDBM |