Decision Memo Completed

Tecuya Ridge Shaded Fuelbreak Project

Los Padres National Forest Kern, California Los Padres National Forest All Units

Healthy Forest Thinning Project within areas at risk or currently being impacted by insects.

Location

Kern County, Tecuy Ridge

Project timeline

1
Scoping Start
03/14/2018
2
Decision
07/2022 (Estimated)
3
Implementation
08/2022 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityBiomass; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Special Products Sales; Noxious Weed Treatments; Timber Sales (Salvage); Timber Sales (Green)
Tecuya Ridge Shaded Fuelbreak ProjectDecision Signed Date: 04/09/2019 (FS Withdrawn, Constrained Due to Litigation)
Tecuya Ridge Shaded Fuelbreak Project - Revised Decision MemoDecision Signed Date: 07/01/2022
ForestsLos Padres National Forest
DistrictsMt. Pinos Ranger District
Legal Land DescriptionT9N, R19W, Sec. 18,28,29,30,31,32,33 SBM. T9N, R20W, Sec. 18,19,20,21,22,23,24,25,27,28,29 SBM. T9N, R21W, Sec. 13,14,15,23,24 SBM.
Forest productsVegetation management (other than forest products)Fuels management