Drill up to four test wells at the proposed fire station rebuild site along the Nacimiento-Fergusson Road to determine whether adequate water is present to support fire station operations.
Location
Chalk Peak Inventoried Roadless Area near boundary with Fort Hunter Liggett
Project timeline
1
Scoping Start
12/13/2023
2
Decision
03/2024 (Estimated)
3
Implementation
04/2024 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Facility Improvements/Construction |
| Nacimiento-Fergusson Station Rebuild Water Test Drilling Project | Decision Signed Date: 03/13/2024 (FS Withdrawn) |
| Forests | Los Padres National Forest |
| Districts | Monterey Ranger District |
| Legal Land Description | SW 1/4 S.29 and SE 1/4 S.30, T.22S, R.6E, Mt. Diablo Meridian |