Environmental Assessment Cancelled

Grey Eagle Mine Restorations

Mendocino National Forest Colusa; Glenn, California Grindstone Ranger District

(Cancelled due to low probability of foreseeable funding) Remove waste rock from adjacent streams, stabilize areas disturbed by mining activities, install surface drainage features in the access roads.

Location

Lovelady Ridge and Red Mountain areas

Project timeline

1
Scoping Start
04/06/2009
2
Comment Period
11/2011 (Estimated)
3
Decision
02/2012 (Estimated)
4
Implementation
09/2012 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityWatershed Improvements
ForestsMendocino National Forest
DistrictsGrindstone Ranger District
Legal Land DescriptionSec 25 T21N R7W; Sec 17, 18 T16N R7W MDBM
Watershed management