Removal of buildings and other infrastructure at the Fouts Springs facility and restore back to a natural setting.
Location
Fouts Springs
Project timeline
1
Scoping Start
01/14/2015
2
Comment Period
07/30/2015
3
Objection Period Start
09/17/2015
4
Decision
01/2016 (Estimated)
5
Implementation
01/2016 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Special Use Authorizations |
| Forests | Mendocino National Forest |
| Districts | Mendocino National Forest All Units |
| Legal Land Description | T18N R7W Sec. 5 |