Development of a Wild and Scenic Comprehensive River Management Plan (CRMP) for Bautista Creek, the North Fork of the San Jacinto River, Palm Canyon Creek and Fuller Mill Creek. Occurs within Hixon Flat, Rouse Hill, and Pyramid Peak A IRAs.
Location
Segments of Palm Canyon Creek, Bautista Creek, Fuller Mill Creek and the North Fork of the San Jacinto River
Project timeline
1
Scoping Start
12/11/2019
2
Comment Period
02/18/2020
3
Objection Period Start
11/30/2020
4
Decision
02/2022 (Estimated)
5
Implementation
02/2022 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Plan Creation/Revision |
| DN and FONSI Comprehensive River Management Plan SBNF | Decision Signed Date: 02/25/2022 |
| Forests | San Bernardino National Forest |
| Districts | San Jacinto Ranger District |
| Legal Land Description | Not Applicable |