Installation of a new 13,340 foot fiber optic cable by Southern California Edison between the SCE Arrowhead District Office and the Strawberry Peak Comm Site building using existing overhead distribution poles and under NFS road 2N72.
Location
Between SCE Arrowhead District Office in the town of Rimforest to the Strawberry Peak Comm Site building
Project timeline
1
Scoping Start
08/20/2012
2
Comment Period
08/20/2012
3
Decision
01/2013 (Estimated)
4
Implementation
03/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| SCE Strawberry Peak Fiber Optic Cable | Decision Signed Date: 01/14/2013 Legal Notice Date: 01/17/2013 |
| Forests | San Bernardino National Forest |
| Districts | Arrowhead Ranger District |
| Legal Land Description | Sections 19, 20, 29 & 30 of T2N, R3W |