Big Bear Municipal Water District wants to take precautionary measures to secure existing fractured rocks located on either side of the dam in order to prevent damage to the dam in the event it is overtopped.
Location
T2N, R1W, Section 22
Project timeline
1
Scoping Start
04/16/2014
2
Decision
07/2014 (Estimated)
3
Implementation
08/2014 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Big Bear Municipal Water District Dam Rock Jack Project | Decision Signed Date: 07/21/2014 |
| Forests | San Bernardino National Forest |
| Districts | Big Bear Ranger District |
| Legal Land Description | T2N, R1W, Section 22 |