Environmental Assessment Cancelled

MTRD 2017 Road Decommissioning and Watershed Improvement

San Bernardino National Forest San Bernardino, California Big Bear Ranger District

This project would decommission system roads, and redesignate one system road as open to administrative use only. Project emphasis is on the Holcomb Valley Baldwin Lake Special Interest Area, with two roads beyond the SIA.

Location

Mountaintop Ranger District

Project timeline

1
Scoping Start
03/2018 (Estimated)
2
Comment Period
06/2019 (Estimated)
3
Objection Period Start
08/2019 (Estimated)
4
Decision
10/2019 (Estimated)
5
Implementation
12/2019 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Species Habitat Improvements; Watershed Improvements
ForestsSan Bernardino National Forest
DistrictsBig Bear Ranger District
Legal Land DescriptionNot Applicable
Watershed managementRoad managementWildlife, fish, rare plants