Decision Memo Completed

Robert Smith & Dorothy Mihaly, Pinewood, water transmission line, permit reissuance

San Bernardino National Forest Riverside, California San Jacinto Ranger District

Reissue permit for 30 years for 52' (fifty-two feet) of pipeline (0.001 acres) for transporting permittees' ground water across USFS from private land to private land. Plastic tubing is attached in the summer then removed in winter.

Location

Pinewood Community near Black Mt. and Fuller Mill Ck. Pipe crosses extreme south east corner of USFS Section 14 as it transports water from private land in Section 13 to private land in Section 23.

Project timeline

1
Scoping Start
05/17/2016
2
Decision
08/2016 (Estimated)
3
Implementation
10/2016 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Robert Smith & Dorothy Mihaly, Pinewood, water transmission line, permit reissuanceDecision Signed Date: 08/30/2016
ForestsSan Bernardino National Forest
DistrictsSan Jacinto Ranger District
Legal Land DescriptionTownship 4 South, Range 2 East, SE 1/4 of the SE 1/4 of the SE 1/4 of the SE 1/4 of section 14, San Bernardino Base Meridian on the San Jacinto Peak Quadrangle
Special use management