Approve continued operation, maintenance and use of existing distribution and transmission powerlines and infrastructure for Southern California Edison located within designated corridors on the San Bernardino National Forest.
Location
Existing transmission lines within the San Bernardino National Forest Boundaries.
Project timeline
1
Scoping Start
03/13/2018
2
Comment Period
05/20/2019
3
Decision
02/2019 (Estimated)
4
Implementation
01/2020 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Southern California Edison Company Master Permit Renewal | Decision Signed Date: 02/05/2019 |
| Forests | San Bernardino National Forest |
| Districts | San Bernardino National Forest All Units |
| Legal Land Description | Not Applicable |