Decision Memo Completed

Southern California Edison Company Master Permit Renewal

San Bernardino National Forest Riverside; San Bernardino, California San Bernardino National Forest All Units

Approve continued operation, maintenance and use of existing distribution and transmission powerlines and infrastructure for Southern California Edison located within designated corridors on the San Bernardino National Forest.

Location

Existing transmission lines within the San Bernardino National Forest Boundaries.

Project timeline

1
Scoping Start
03/13/2018
2
Comment Period
05/20/2019
3
Decision
02/2019 (Estimated)
4
Implementation
01/2020 (Estimated)

NEPA / regulatory detail

Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Southern California Edison Company Master Permit RenewalDecision Signed Date: 02/05/2019
ForestsSan Bernardino National Forest
DistrictsSan Bernardino National Forest All Units
Legal Land DescriptionNot Applicable
Special use management