An ecological restoration project in the Oak Ridge area of the Greenhorn Mountains. This project will implement sustainable forest practices by improving wildland fire safety, wildlife habitat, and economic use of forest by-products.
Location
Oak Ridge area, Greenhorn Mountains
Project timeline
1
Scoping Start
05/16/2011
2
Comment Period
04/23/2013
3
Decision
07/2013 (Estimated)
4
Implementation
11/2013 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green) |
| Rancheria Forest Restoration Project | Decision Signed Date: 07/05/2013 Legal Notice Date: 07/05/2013 |
| Forests | Sequoia National Forest |
| Districts | Kern River Ranger District |
| Legal Land Description | T25 and 26S, R31 and 32E, MDBM |