Decision Memo · Western Divide Ranger District · updated 6/9/2025
The Monache Gathering Site, also known as Camp 1 and Camp 2, are found near Johnsondale on Meadow Road, south of Camp Whitsett. Camp 2 is north of Bone Creek and Camp 1 is south. · Tulare, California

Mitigation of hazard trees on Camps 1 and 2 to allow for safe use of the recreation sites through removal and burning of piled materials.

Facility management
Scoping Start
04/03/2025
Decision
06/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
Nancy Kelly · nancy.kelly@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (13), 36 Cfr 220.6(E)(13)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDispersed Recreation Mgmt.
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 5/13/2025
Shirley Peak in Section 32, T.25S, R.32E. MDB&M. · Kern, California

Upgrading existing microwave system at Shirley Peak to an 8 GHz band, replacing existing Forest Service building, replacng existing towers, and building new building and towers.

Special use management
Scoping Start
07/01/2023
Decision
03/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
Lisa Gammell · lisa.gammell@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Special Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 5/8/2025
The siphon runs from the hatchery (14415 Sierra Way, Kernville) northward approximately 0.5 mile to the KR3 SCE Power Station. · Kern, California

The California DFW proposes removing existing siphon and pipeline and installing new ones in same footprint at the fish hatchery.

Wildlife, fish, rare plantsFacility management
Scoping Start
02/17/2025
Decision
05/2025 (Estimated)
Implementation
06/2025 (Estimated)
Project documents
Ronald Rozar · Ronald.Rozar@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (21), 36 Cfr 220.6(E)(21)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Species Population Enhancements
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 12/17/2024
FS Road 21S01 at Jackass Creek. FS 21S01 is a maintenance level 2 road that provides access to Jackass Meadow, but dead ends approximately 3 miles from the junction of Sherman Pass Road (22S05). · Tulare, California

Culvert removal and stream channel restoration in the crossing. Old culvert would be replaced by a bridge or bottomless-arch culvert. APE is approximately 0.25 to 0.35 acres. All disturbance would be confined to existing roadway.

Wildlife, fish, rare plantsWatershed management
Scoping Start
11/08/2024
Decision
12/2024 (Estimated)
Implementation
01/2025 (Estimated)
Project documents
Keith Stone · keith.stone@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements; Species Population Enhancements; Watershed Improvements
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 12/17/2024
Off FS Road 21S01, approximately 3 miles from the Junction of Sherman Pass Road (22S05). · Tulare, California

Need to improve Jackass Meadow hydrologic function by stabilizing and elevating the meadow grade and prevent further degradation. Will install Beaver Dam Analog (BDA) structures.

Watershed management
Scoping Start
11/08/2024
Decision
12/2024 (Estimated)
Implementation
01/2025 (Estimated)
Project documents
Keith Stone · keith.stone@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (25), 36 Cfr 220.6(E)(25)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements; Species Population Enhancements; Watershed Improvements
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Environmental Impact Statement · Sequoia National Forest All Units · updated 11/26/2024
Giant Sequoia National Monument within the Hume Lake and Western Divide Ranger Districts of the Sequoia National Forest. · Fresno; Tulare, California

Establish management direction for the land and resources within the Giant Sequoia National Monument. (Monument was established in April 2000.)

Land management planning
NOI in Federal Register
03/16/2009
DEIS NOA in Federal Register
08/06/2010
FEIS NOA in Federal Register
09/07/2012
Decision
08/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
Annette Fredette · afredette@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation219 (1982)
Project ActivityPlan Amendment
Giant Sequoia National Monument Mgmt Plan 2012 FEIS Record of DecisionDecision Signed Date: 08/08/2012 Legal Notice Date: 09/07/2012
ForestsSequoia National Forest
DistrictsHume Lake Ranger District; Western Divide Ranger District
Legal Land DescriptionApproximately 327,769 acres. Located in Fresno and Tulare Counties, California.
Decision Memo · Western Divide Ranger District · updated 8/16/2024
Western slope of the Sierra Nevada within areas approximately 10 to 20 miles north and east of Springville, CA, adjacent to or near the California State Route 190 corridor and Balch Park Road · Tulare, California

Management of debris piles (resulting from the 2020 Castle Fire) located within Southern California Edison (SCE) right-of-ways through removal and chipping/spreading to reduce fuel loading.

Fuels management
Scoping Start
01/17/2024
Decision
10/2024 (Estimated)
Implementation
10/2024 (Estimated)
Project documents
Sarah Dezelin · Sarah.Dezelin@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (11), 36 Cfr 220.6(E)(11)
Special AuthorityNational Fire Plan - Healthy Forests Initiative Ce
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels)
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Western Divide Ranger District · updated 8/16/2024
A cluster of treatments north of Johnsondale (eastern portion of the Windy Fire). Another cluster of treatments near the Sugarloaf community on the southernmost portion of the windy fire perimeter. · Tulare, California

Management of debris piles (resulting from the 2021 Windy Fire) located within and adjacent to Southern California Edison (SCE) right-of-ways through removal and chipping/spreading to reduce fuel loading.

Vegetation management (other than forest products)
Scoping Start
01/29/2024
Decision
10/2024 (Estimated)
Implementation
10/2024 (Estimated)
Project documents
Sarah Dezelin · Sarah.Dezelin@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (11), 36 Cfr 220.6(E)(11)
Special AuthorityNational Fire Plan - Healthy Forests Initiative Ce
Notice and Comment RegulationNot Subject to Regulations
Project ActivityBiomass; Fuel Treatments (Non-Activity Fuels)
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Western Divide Ranger District · updated 4/18/2024
Spur Roads No. 21S12B, 21S25A, 21S25B, 21S25C, 21S25D and Road No. 21S25 east from its intersection with 21S25B. · Tulare, California

This project will consider decommissioning several roads/segments in the Black Mtn giant sequoia grove

Special area managementWatershed managementRoad management
Scoping Start
10/2017 (Estimated)
Comment Period
11/2017 (Estimated)
Objection Period Start
01/2018 (Estimated)
Decision
02/2018 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
Michael Brumbaugh · michael.brumbaugh@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Travel Management; Watershed Improvements
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionT21S, R31E, Sections 1, 7, 12
Decision Memo · Kern River Ranger District · updated 4/18/2024
Kernville area · Kern, California

Maintenance & operation of a water transmission line (less than 12 inches diameter) and enclosure with reservoir covering 0.04 acres

Special use management
Scoping Start
06/2020 (Estimated)
Decision
08/2020 (Estimated)
Implementation
09/2020 (Estimated)
Project documents
Keith Fox · Keith.Fox@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSection 14, T25S, R33E, MDB&M
Decision Memo · Hume Lake Ranger District · updated 4/15/2024
In previously planted stands in the Rough and KNP Fire footprints, and Eshom restoration project areas across the Hume Lake Ranger District. · Fresno; Tulare, California

To use herbicides such as Glyphosate and Triclopyr within the approximately 2,060 acres in the Rough,Eshom/KNP fire areas to improve planted seedling survival. through reduced shrub competition.

Vegetation management (other than forest products)
Scoping Start
07/25/2023
Decision
04/2024 (Estimated)
Implementation
06/2024 (Estimated)
Project documents
Marianne Emmendorfer · marianne.emmendorfer@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (25), 36 Cfr 220.6(E)(25)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
Reforestation Using Herbicide Decision MemoDecision Signed Date: 04/11/2024
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13-14S, R27-29E, MDBM
Environmental Assessment · Western Divide Ranger District · updated 12/28/2023
Within Castle Fire footprint, outside of wilderness, adjacent to Highway 190, Mountain Home State Park, and local communities, includes Giant Sequoia National Monument lands · Tulare, California

To restore and promote a healthy forest ecosystem; to establish forest conditions, to promote resilient forest conditions and to establish and maintain low surface and ladder fuel conditions

Fuels managementVegetation management (other than forest products)
Scoping Start
01/28/2021
Comment Period
02/01/2023
Objection Period Start
05/20/2023
Decision
12/2023 (Estimated)
Implementation
03/2024 (Estimated)
Project documents
Gretchen Fitzgerald · gretchen.fitzgerald2@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
Castle Fire Ecological Restoration Project Decision NoticeDecision Signed Date: 12/28/2023
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionTownship 18S Range 29-30, 33E, T19S R29-31E, T20S R30-34E; T21S R31-34 E
Environmental Assessment · Western Divide Ranger District · updated 12/28/2023
Project activities will occur within the perimeter of the Windy Fire (2021) · Tulare, California

The project will promote forest resilience and ecological integrity by reducing fuel loads, reforestation, wildlife habitat improvement and hydrologic improvement activities.

Vegetation management (other than forest products)Carbon stewardshipFuels management
Scoping Start
09/02/2022
Comment Period
03/21/2023
Objection Period Start
08/04/2023
Decision
12/2023 (Estimated)
Implementation
03/2024 (Estimated)
Project documents
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Salvage)
Windy Fire Restoration Project Decision Notice and FONSIDecision Signed Date: 12/28/2023
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Hume Lake Ranger District · updated 12/4/2023
The project is located between state highway 180 and Forest Road 14S02 (Burton Pass Road). · Fresno; Tulare, California

Treat up to 6,700 acres through thinning, sanitation, mastication and prescribed burn to improve forest health and wildlife habitat, and reduce fuels in Tenmile Creek drainage.

Wildlife, fish, rare plantsWatershed managementFuels managementRoad managementVegetation management (other than forest products)Forest products
Scoping Start
09/21/2021
Comment Period
03/16/2023
Objection Period Start
06/01/2023
Decision
12/2023 (Estimated)
Implementation
03/2024 (Estimated)
Project documents
Jarrett Bleicher · jarrett.bleicher@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Road Maintenance; Timber Sales (Salvage); Timber Sales (Green)
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13-14S, R28E, MDB&M
Environmental Assessment · R5 - Pacific Southwest Region All Units · updated 6/16/2023
Certain national forest roads, trails and facilities within recent fire areas. · Butte; Colusa; Del Norte; Fresno; Glenn; Humboldt; Inyo; Kern; Lake; Lassen; Madera; Mendocino; Mono; Plumas; Shasta; Siskiyou; Tehama; Trinity; Tulare, California

Hazard tree felling and removal is proposed to reduce public safety hazards along portions of certain roads, trails and facilities within nine national forests. We expect to complete three zone-level analyses and nine decisions.

Recreation managementFuels managementRoad management
Scoping Start
10/25/2021
Comment Period
04/11/2022
Objection Period Start
10/26/2022
Decision
06/2023 (Estimated)
Implementation
03/2023 (Estimated)
Project documents
Laura Hierholzer · laura.hierholzer@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityDeveloped Site Management; Fuel Treatments (Non-Activity Fuels); Trail Management; Road Maintenance
R5HT Final DN Six RiversDecision Signed Date: 06/15/2023
R5HT Final DN KlamathDecision Signed Date: 06/07/2023
R5HT Final DN MendocinoDecision Signed Date: 06/12/2023
R5HT Final DN Shasta-TrinityDecision Signed Date: 06/13/2023
R5HT Final DN PlumasDecision Signed Date: 12/19/2022
R5HT Final DN LassenDecision Signed Date: 12/19/2022
R5HT Final DN SequoiaDecision Signed Date: 01/17/2023
R5HT Final DN InyoDecision Signed Date: 01/17/2023
ForestsInyo National Forest; Klamath National Forest; Lassen National Forest; Mendocino National Forest; Six Rivers National Forest; Plumas National Forest; Sequoia National Forest; Shasta Trinity National Forest; Sierra National Forest
DistrictsInyo National Forest All Units; Klamath National Forest All Units; Lassen National Forest All Units; Mendocino National Forest All Units; Six Rivers National Forest All Units; Plumas National Forest All Units; Sequoia National Forest All Units; Shasta Trinity National Forest All Units; Sierra National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Western Divide Ranger District · updated 2/2/2023
Freeman Creek and Starvation Creek · Tulare, California

Reforestation in high severity burn areas of the Castle and Windy Fires

Vegetation management (other than forest products)
Scoping Start
02/02/2023
Decision
02/2023 (Estimated)
Implementation
04/2023 (Estimated)
Project documents
Gretchen Fitzgerald · gretchen.fitzgerald2@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements; Species Habitat Improvements
20230202Freeman&StarvationPlantingDMDecision Signed Date: 02/02/2023
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 1/20/2023
Project area is within the burned area of the 2002 McNally Fire along portions of Sherman Pass Rd and Lookout Mountain Rd. · Kern, California

Approximately 700 acres of land burned by the 2002 McNally Fire will be re-planted.

Vegetation management (other than forest products)
Scoping Start
01/18/2023
Decision
01/2023 (Estimated)
Implementation
04/2023 (Estimated)
Project documents
NEPA / regulatory detail
Categorical Exclusion32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
McNally Reforestation DMDecision Signed Date: 01/19/2023
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Hume Lake Ranger District · updated 11/1/2022
Proposed campground would be constructed on both north and south sides of Forest Road No. 13S09 (Tenmile Road) adjacent to the location of Forest Roads Nos. 13S09J and 13S33. · Fresno, California

Construct a new campground with a mix of campsite types (e.g., tent, RV, family groups up to 20 people, yurts) consisting of a vehicle parking area and a camping area that will accommodate a picnic table, fire ring, bear box, and a tent pad.

Recreation management
Scoping Start
08/12/2020
Comment Period
08/24/2020
Objection Period Start
08/16/2022
Decision
10/2022 (Estimated)
Implementation
10/2022 (Estimated)
Project documents
Jeremy Dorsey · jeremy.dorsey@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFacility Improvements/Construction
LAVA BUTTE CAMPGROUND DevelopmentDecision Signed Date: 10/31/2022
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13S R28E Sec 25, MDB&M
Environmental Assessment · Hume Lake Ranger District · updated 10/7/2022
Forest Service portion of General's Highway, Big Meadows Road from General's Highway to Heart Meadow turnoff, and Heart Meadow cabin tract access road. · Tulare, California

Fell and remove dead and dying trees posing a falling hazard along General's Highway, Big Meadows Road (FR14S11) to and including Heart Meadow Road (14S02D).

Road managementVegetation management (other than forest products)
Scoping Start
01/22/2020
Comment Period
04/14/2022
Objection Period Start
07/27/2022
Decision
09/2022 (Estimated)
Implementation
06/2023 (Estimated)
Project documents
Marianne Emmendorfer · marianne.emmendorfer@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityBiomass; Road Maintenance; Timber Sales (Salvage)
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13S, R28-29E, MDB&M
Decision Memo · Western Divide Ranger District · updated 10/5/2022
Tule River watershed · Tulare, California

The project will reduce fuel loads and remove ladder fuels through a combination of dead and live tree removal and duff removal around the base of monarch Giant Sequoia trees.

Vegetation management (other than forest products)
Scoping Start
07/22/2022
Decision
07/2022 (Estimated)
Implementation
08/2022 (Estimated)
Project documents
Gretchen Fitzgerald · gretchen.fitzgerald2@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (25), 36 Cfr 220.6(E)(25)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
Decision Memorandum for the Chief R5 Emergency Response Giant SequoiaDecision Signed Date: 07/22/2022
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Hume Lake Ranger District · updated 10/5/2022
Portion of Grant Grove in Giant Sequoia National Monument, and Abbott Creek Grove. · Fresno, California

Hand cut and pile around large sequoias, burn piles, then underburn to treat surface and ladder fuel to reduce risk of stand replacement in high severity wildfire. Improve conditions for controlled burns or managed wildfire in the groves.

Vegetation management (other than forest products)
Scoping Start
07/22/2022
Decision
07/2022 (Estimated)
Implementation
10/2022 (Estimated)
Project documents
Marianne Emmendorfer · marianne.emmendorfer@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
DECISION MEMORANDUM_FOR THE CHIEF_R5_EmergencyResponse_GiantSequoiaDecision Signed Date: 07/22/2022
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Hume Lake Ranger District · updated 6/28/2022
Portion of Big Stump Grove bisected by State Highway 180, Redwood Mountain Grove,and area in between southwest of Kings Canyon National Park. · Fresno; Tulare, California

Proposal to reduce fuels buildup in a portion of Big Stump Giant Sequoia Grove through prescribed burning to protect nearby facilities and begin reintroducing fire into the grove.

Fuels management
Scoping Start
02/14/2014
Comment Period
05/26/2018
Objection Period Start
07/23/2018
Decision
09/2018 (Estimated)
Implementation
10/2018 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels); Species Habitat Improvements
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT14S, R28E, MDB&M
Decision Memo · Sequoia National Forest All Units · updated 6/28/2022
Project includes roads affected by the 2016 Cedar Fire in and near the Bull Run Creek area. · Kern; Tulare, California

Felling and removing hazard trees along forest roads affected by the Cedar Fire, drought, and bark beetles in the Bull Run Creek area.

Vegetation management (other than forest products)Fuels managementRoad management
Scoping Start
02/14/2017
Decision
08/2017 (Estimated)
Implementation
09/2017 (Estimated)
Project documents
Chris Sanders · csanders@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (11), 36 Cfr 220.6(E)(11)
Special AuthorityNational Fire Plan - Healthy Forests Initiative Ce
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance
BULL RUN ROADSIDE HAZARD TREE MITIGATION PROJECTDecision Signed Date: 08/30/2017
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District; Kern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Hume Lake Ranger District · updated 6/28/2022
Adjacent to specific developed recreation sites, fuelbreaks and special use operated sites across the district. also locations where material pulled out of recreation sites has been piled or decked. · Fresno; Tulare, California

To safely operate specified recreation sites and fuelbreaks; pile & burn, and remove as wood/timber products a portion of the slash created during the hazard tree felling resulting from the drought, insect and fire mortality from 2012-2016.

Special use managementRecreation managementFuels managementRoad managementFacility management
Scoping Start
12/12/2017
Decision
03/2018 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Fuel Treatments (Non-Activity Fuels); Dispersed Recreation Mgmt.; Special Use Authorizations; Road Maintenance
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Kern River Ranger District · updated 6/28/2022
Horse Meadow, Kern Plateau, approximately 10 miles north of Lake Isabella, CA, off of Cherry Hill/ Sherman Pass Roads · Tulare, California

Ecological restoration & hazardous fuels treatment on 6153 acres in the wildland urban interface of the Horse Meadow Community. Treatments would employ mechanical and hand thinning, and prescribed fire, with some commercial timber harvest.

Vegetation management (other than forest products)Fuels managementForest products
Scoping Start
10/16/2012
Comment Period
11/02/2012
Objection Period Start
12/13/2013
Decision
02/2014 (Estimated)
Implementation
06/2014 (Estimated)
Project documents
John Gomez · johngomez@fs.fed.us
NEPA / regulatory detail
Special AuthorityHfra Title I: Wildland-Urban Interface
Notice and Comment Regulation218 (2013) HFRA
Project ActivityForest Vegetation Improvements; Timber Sales (Green)
Decision Notice and FONSI Joey Healthy Forest and Fuels Reduction ProjectDecision Signed Date: 02/24/2014
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT. 23 and 24 S., R. 33 and 34 E., Mount Diablo Base and Meridian (MDB&M).
Decision Memo · Hume Lake Ranger District · updated 6/28/2022
Hume Lake Ranger District · Fresno; Tulare, California

Masticate small trees (less than 10 inches dbh) and brush causing overstocked conditions in plantations near Kirkland Meadow. Underburn or pile and burn fuel concentrations. Leave 80-120 trees per acre and pockets of untreated shrubs for wildlife.

Vegetation management (other than forest products)
Scoping Start
08/09/2011
Decision
09/2017 (Estimated)
Implementation
10/2017 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13-14S, R28-29E, MDB&M
Decision Memo · Western Divide Ranger District · updated 6/28/2022
Long Meadow is located just below Long Meadow Giant Sequoia Grove · Tulare, California

Restore meadow functioning by repairing headcuts in Long Meadow by establishing a low gradient step pool system from the bottom of the meadow up to the headcut.

Watershed management
Scoping Start
12/30/2011
Comment Period
03/16/2013
Decision
07/2013 (Estimated)
Implementation
09/2013 (Estimated)
Project documents
Robin Galloway · rgalloway@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityWatershed Improvements
Long Meadow Restoration ProjectDecision Signed Date: 07/19/2013 Legal Notice Date: 07/23/2013
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionT22S., R31E., Sections 26 and 35
Decision Memo · Sequoia National Forest All Units · updated 6/28/2022
This project is located along approximately 35 miles of roads within the Pier Fire area. · Tulare, California

Felling and removing hazard trees along roads, maintaining roads, and restoring ground cover and vegetation in the Pier fire area.

Fuels managementForest products
Scoping Start
02/13/2018
Decision
10/2018 (Estimated)
Implementation
12/2018 (Estimated)
Project documents
Amarina Wuenschel · amarinawuenschel@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (11), 36 Cfr 220.6(E)(11)
Special AuthorityNational Fire Plan - Healthy Forests Initiative Ce
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Timber Sales (Salvage)
PIER FIRE ROADSIDE HAZARD TREE MITIGATION PROJECTDecision Signed Date: 10/03/2018
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionT20S, R30E, Sections 13-14,22-23; T20S, R31E, Sections 7-8,16-17,20-22,26-29; T21S, R30E, Sections 1 and 12; T21S, R31E, Sections 3,6-10,16-17
Environmental Assessment · Western Divide Ranger District · updated 6/28/2022
Adjacent to the community of Ponderosa and Quaker Meadow Camp. · Tulare, California

This project would reduce flammable vegetation within the Ponderosa Wildland Urban Interface Zone. Proposed under the Healthy Forests Restoration Act. Addresses immediate need around Ponderosa and Quaker Meadows.

Fuels management
Scoping Start
03/03/2006
Comment Period
07/18/2008
Decision
02/2009 (Estimated)
Implementation
05/2009 (Estimated)
Project documents
Robert Sanders · rsanders@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (10)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels)
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionSections 4, 5, 7-10, 15-18, & 20-22, T.21S., R.32E., MDM.
Environmental Assessment · Kern River Ranger District · updated 6/28/2022
T25-26S, R32E, MDB&M · Kern, California

Greenhorn Mountains fuels reduction project within the Greenhorn East and West compartments, including the Tillie Creek, French Gulch, and Cedar Creek watersheds. The Injunction on this project was Vacated on 8/24/2011.

Forest productsFuels management
Scoping Start
05/28/2010
Comment Period
09/18/2010
Decision
07/2011 (Estimated)
Implementation
09/2011 (Estimated)
Project documents
Steve Anderson · swanderson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels); Timber Sales (Green)
Affirmation of Existing Decision Dated December 11, 1998 Rev Ice TS & FRPDecision Signed Date: 07/05/2011
Affirmation of Existing Decision Dated December 11, 1998 Revised Ice TimberDecision Signed Date: 07/05/2011 Legal Notice Date: 07/09/2011
ForestsSequoia National Forest
DistrictsKern River Ranger District
Decision Memo · Sequoia National Forest All Units · updated 6/28/2022
This project decision would include forest roads in the Giant Sequoia National Monument affected by the Cedar Fire. · Kern; Tulare, California

Felling and removing hazard trees along forest roads affected by the Cedar Fire, drought, and bark beetles in the Spear Creek area of the Giant Sequoia National Monument.

Vegetation management (other than forest products)Fuels managementRoad management
Scoping Start
05/01/2017
Decision
01/2018 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
George Powell · gpowell@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (11), 36 Cfr 220.6(E)(11)
Special AuthorityNational Fire Plan - Healthy Forests Initiative Ce
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District; Kern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 6/28/2022
Alta Sierra community, Wildland Urban Interface · Kern, California

Increase forest stand resiliency to insects and disease by thinning trees on approximately 1,100 acres within the wildland urban interface (WUI) surrounding Alta Sierra.

Fuels managementForest products
Scoping Start
12/21/2015
Decision
06/2017 (Estimated)
Implementation
09/2016 (Estimated)
Project documents
Steve Anderson · swanderson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (13), 36 Cfr 220.6(E)(13); 32.3 (5)
Special AuthorityHfra Title Vi: Insect And Disease Projects
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Timber Sales (Salvage); Timber Sales (Green)
SUMMIT HEALTHY FOREST PROJECT REVISED DECISION MEMODecision Signed Date: 06/29/2017
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT25S, R32E; MDB&M
Democrat Fence Completed
Decision Memo · Kern River Ranger District · updated 6/3/2022
Cow Flat grazing allotment; top of hill/cliff above HWY 178. · Kern, California

Installation of fencing on Cow Flat grazing allotment to prevent cattle from ranging onto steep hillsides and falling on the the roadway below. The fence will improve public safety and mitigate loss of stock.

Grazing management
Scoping Start
04/01/2022
Decision
06/2022 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
NEPA / regulatory detail
Categorical Exclusion32.2 (9), 36 Cfr 220.6(E)(9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Allotment Management; Grazing Structural Improvements
Democrat Fence DM SIGNEDDecision Signed Date: 06/02/2022
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Western Divide Ranger District · updated 5/5/2022
Lloyd Meadow Road (22S82) and side roads (20S67, 20S77 and 20S78) · Tulare, California

Post Castle Fire hazard tree mitigation for Lloyd Meadow Road and side roads

Fuels managementRoad management
Scoping Start
11/02/2020
Decision
05/2022 (Estimated)
Implementation
06/2022 (Estimated)
Project documents
Steven Caracciolo · Steven.Caracciolo@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Road Maintenance
1950 Lloyd Meadow Rd Hazard Tree Mitigation PDMDecision Signed Date: 05/03/2022
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Western Divide Ranger District · updated 4/21/2022
In the vicinity of Sequoia Crest, on adjacent National Forest lands · Tulare, California

Tree planting within high severity burn areas associated with the Castle Fire (2020)

Vegetation management (other than forest products)
Scoping Start
03/21/2022
Decision
04/2022 (Estimated)
Implementation
04/2022 (Estimated)
Project documents
Gretchen Fitzgerald · gretchen.fitzgerald2@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
Green Side tree planting 2022 DMDecision Signed Date: 04/18/2022
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Environmental Impact Statement · Kern River Ranger District · updated 9/28/2021
Piute Mountains, south of Lake Isabella, California. · Kern, California

A collaborative process to develop a travel management plan for the Piute Mountains area.

Recreation managementLand management planningHeritage resource management
NOI in Federal Register
02/18/2011
DEIS NOA in Federal Register
02/18/2011
FEIS NOA in Federal Register
09/2021 (Estimated)
Objection Period Start
09/2012 (Estimated)
Decision
04/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
Norman Leonard · Norman.Leonard@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityTravel Management
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionPiute Mountains, Sequoia National Forest
Decision Memo · Sequoia National Forest All Units · updated 8/25/2021
Castle Fire area located in the Western Divide Ranger District. · Tulare, California

Hazard tree mitigation for the safety of forest users along approximately 130 miles of NFS roads, and within and around recreation and administrative sites within the Castle Fire perimeter.

Fuels managementRoad management
Scoping Start
11/02/2020
Decision
08/2021 (Estimated)
Implementation
09/2021 (Estimated)
Project documents
Steven Caracciolo · Steven.Caracciolo@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.12 (3), 36 Cfr 220.6(D)(3); 32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Road Maintenance
1950_Castle Fire_NorthRoad_HazardTreeMitigationProject DecisionMemoFinalDecision Signed Date: 08/25/2021
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Sequoia National Forest All Units · updated 7/1/2021
Cow Camp, Maggie Lake, Twin Lake, Deadman Lake, West Meadow, Groundhog within the Golden Trout Wilderness · Tulare, California

Authorizing a 10 year outfitting and guiding special use permit for Balch Park Pack Station for horse back related/riding activities on trails, campsites within the Golden Trout Wilderness area on the Western Divide RD, Sequoia NF.

Special use management
Scoping Start
06/30/2016
Decision
11/2020 (Estimated)
Implementation
12/2020 (Estimated)
Project documents
Lisa Gammell · lisa.gammell@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 7/1/2021
Located near French Gulch Peninsula at Lake Isabella, on the Kern River Ranger District. · Kern, California

Issue new permit for one building (20 ft X 20 ft) and an associated parking area (one acre), to be used in conjuction with boat patrols on Lake Isabella. SUP to be issued for 10 years. (SUP was never issued. Previously under an ACOE lease)

Special use managementLand ownership management
Scoping Start
12/2017 (Estimated)
Decision
07/2018 (Estimated)
Implementation
08/2018 (Estimated)
Project documents
Tricia Maki · triciamaki@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityOrder Creation/Modification
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNW 1/4 Sec. 9, T.26S., R.33E., MDM. Approximately one (1) acre. Kern County.
Environmental Impact Statement · Kern River Ranger District · updated 7/1/2021
Kern Plateau, Kern River Ranger District. · Tulare, California

Analysis of OHV trail as per the Sequoia Land Management Plan Mediated Settlement Agreement. Revised DEIS published August 2002.

Recreation management
NOI in Federal Register
10/01/1993
DEIS NOA in Federal Register
08/01/2002
FEIS NOA in Federal Register
06/2016 (Estimated)
Objection Period Start
04/2016 (Estimated)
Decision
09/2016 (Estimated)
Implementation
10/2016 (Estimated)
Project documents
Tricia Maki · tricia.maki@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityTrail Management
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT.22-23S., R.34E., MDM. Seven (7) miles.
Decision Memo · Kern River Ranger District · updated 6/29/2021
Kernville area · Kern, California

Operation and maintenance of a water irrigation ditch

Special use management
Scoping Start
12/2017 (Estimated)
Decision
02/2018 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
Tricia Maki · tricia.maki@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSection 10, T25S, R33E, MDB&M
Decision Memo · Kern River Ranger District · updated 6/10/2021
Dome Land Wilderness · Tulare, California

FLPMA road special use permit (SUP) to be reissued for 10 years, with no changes and no ground disturbing activities.

Special use management
Scoping Start
10/03/2008
Decision
06/2018 (Estimated)
Implementation
07/2018 (Estimated)
Project documents
Tricia Maki · tricia.maki@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSections 26, 27, 34, T23S, R35 E, MDB&M
Environmental Assessment · Kern River Ranger District · updated 6/8/2021
Greenhorn Creek located in the Greenhorn Mountains, on Kern River Ranger District. · Kern, California

Placer mining operations for the exploration and extraction of gold from the stream channel in Greenhorn Creek and maintenance of the access roads.

Minerals and geologyRoad managementSpecial use management
Scoping Start
12/15/2008
Comment Period
12/19/2009
Objection Period Start
06/2015 (Estimated)
Decision
07/2015 (Estimated)
Implementation
07/2015 (Estimated)
Project documents
Alfred Watson · alfred.watson@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityHarzardous Waste Compliance Actions; Minerals Or Geology Plans Of Operations; Road Maintenance
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSections 11 & 12, T.27S., R.31E., MDM. Kern County, CA.
Decision Memo · Hume Lake Ranger District · updated 9/29/2020
Existing planted stands affected by the Rough Fire from Pine Ridge east into Boulder Creek drainage, including planted stands in Converse Basin and Evans Grove Complex giant sequoia groves. · Fresno, California

Improve forest health and reduce fuels in existing plantations, damaged by fire, drought & insects. Restore native species mix & maintain/promote old forest habitat components while reducing safety hazards on roads.

Vegetation management (other than forest products)Fuels managementForest productsWildlife, fish, rare plantsWatershed managementRoad management
Scoping Start
01/08/2020
Decision
09/2020 (Estimated)
Implementation
10/2020 (Estimated)
Project documents
Marianne Emmendorfer · marianne.emmendorfer@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (20), 36 Cfr 220.6(E)(20)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Road Maintenance; Timber Sales (Salvage); Timber Sales (Green)
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13S, R26-29E
Environmental Assessment · Hume Lake Ranger District · updated 7/7/2020
Both resorts are on General's Highway between the junction with Forest Road 14S11 and the Sequoia National Park boundary to the southeast. · Tulare, California

Reconstruct & construct buildings and other infrastructure such as waterlines within the permitted areas for both Stony Creek and Montecito Lake resorts to improve function and visitor services.

Recreation managementFacility managementSpecial use management
Scoping Start
06/24/2019
Comment Period
05/15/2020
Decision
07/2020 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
Diane Bedell · diane.bedell@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityDeveloped Site Management; Special Use Authorizations; Facility Maintenance
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT14S, R29E, Sec. 19 (Montecito) and 32 (Stony)
Decision Memo · Sequoia National Forest All Units · updated 12/31/2019
Near Johnsondale in Section 35, T22S, R32E, MDB&M · Tulare, California

Authorizing a 10-year special use permit for operation and maintenance of a resort.

Special use management
Scoping Start
06/30/2016
Decision
12/2019 (Estimated)
Implementation
12/2019 (Estimated)
Project documents
Lisa Gammell · lisa.gammell@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Sequoia National Forest All Units · updated 11/26/2019
Hume Lake RD 15.9 miles; Kern River RD 91.9 miles, and Western Divide 62 miles of routes are proposed for grooming. · Fresno; Kern; Tulare, California

The Over-Snow Grooming project proposes to groom approximately 170 miles of routes in the Sequoia National Forest and Giant Sequoia National Monument.

Recreation managementRoad management
Scoping Start
02/03/2016
Decision
09/2016 (Estimated)
Implementation
11/2016 (Estimated)
Project documents
Karen Miller · kgmiller@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance
OVER-SNOW GROOMING (2016- Through Winter 2020-2021)Decision Signed Date: 09/26/2016
ForestsSequoia National Forest
DistrictsSequoia National Forest All Units
Legal Land DescriptionNot Applicable
Environmental Assessment · Kern River Ranger District · updated 11/5/2019
Taylor and Long Meadows on the Kern Plateau, accessed from Cherry Hill Road (22S12) · Tulare, California

Proposal to reauthorize an existing grazing permit for the Taylor/Long Allotment located on the Kern Plateau.

Grazing management
Scoping Start
04/23/2013
Comment Period
06/03/2014
Objection Period Start
07/17/2018
Decision
11/2019 (Estimated)
Implementation
11/2019 (Estimated)
Project documents
Steve Anderson · steve.w.anderson@usda.gov
NEPA / regulatory detail
Special AuthorityGrazing, Rescissions Act Of 1995
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityGrazing Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSections 20 & 23, T24S, R34E, MDB&M
Environmental Assessment · Sequoia National Forest All Units · updated 10/25/2019
The project is located in the headwaters of Bull Run Creek, tributary to North Fork Kern River. · Tulare, California

This project is proposed to reduce erosion within Dry Meadow and restore floodplain function and resiliency.

Watershed management
Scoping Start
07/13/2017
Comment Period
04/03/2019
Objection Period Start
06/17/2019
Decision
09/2019 (Estimated)
Implementation
08/2020 (Estimated)
Project documents
Jonathan Markovich · jonathan.markovich@usda.gov
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityWatershed Improvements
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 10/3/2019
Within 150 feet of the following roads and facilities: 22S05 from 22S29 north to Blackrock Station, and 21S03 north to Blackrock Trailhead. · Tulare, California

Removal of hazard trees posing a hazard to two primary roads (22S05 and 21S03), an administrative site (Blackrock Station), and a developed recreation site (Blackrock Trailhead).

Road managementForest productsFuels managementRecreation managementFacility management
Scoping Start
04/10/2006
Comment Period
05/16/2007
Decision
07/2007 (Estimated)
Implementation
08/2007 (Estimated)
Project documents
Susan Porter · smporter@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (3), 36 Cfr 220.6(D)(3); 32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDeveloped Site Management; Road Maintenance; Timber Sales (Salvage)
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSec. 22,23,26,27,34, &35, T.20S., R34E.; Sec. 1,11,12,13,23,24,26, &35, T.21S., R.34E.; and Sec. 1,2,11, &12, T.22S., R.34E., MDM. - 500 acres.
Environmental Assessment · Kern River Ranger District · updated 9/30/2019
Replace and/or install toilet buildings on the Kern Plateau and at various locations on the Kern River Ranger District. · Kern; Tulare, California

Replace existing portable toilets with new vault toilet buildings and/or install new vaults where no permanent toilet facility currently exists.

Recreation management
Scoping Start
01/06/2010
Comment Period
10/27/2010
Decision
12/2010 (Estimated)
Implementation
05/2011 (Estimated)
Project documents
Cheryl Bauer · cabauer@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDeveloped Site Management; Facility Improvements/Construction; Dispersed Recreation Mgmt.
New Toilet Building Installation ProjectDecision Signed Date: 12/03/2010
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionDistrict wide.
Decision Memo · Kern River Ranger District · updated 9/26/2019
Piute Mountains · Kern, California

Restrict access to two historic mines by adding a bat gate and filling an opening.

Minerals and geologyWildlife, fish, rare plants
Scoping Start
09/09/2019
Decision
09/2019 (Estimated)
Implementation
09/2019 (Estimated)
Project documents
Tim Kelly · tim.kelly@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 9/25/2019
Breckenridge Mountain, T28S R31E · Kern, California

Remove up to 100 trees causing signal interference at the Breckenridge Communication Sites.

Forest productsSpecial use management
Scoping Start
02/28/2019
Decision
08/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
Brian Block · brian.block@usda.gov
NEPA / regulatory detail
Categorical Exclusion32.2 (12), 36 Cfr 220.6(E)(12)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTimber Sales (Green)
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 9/20/2019
Tulare County, California Along Sirretta Road No. 22S21 and Sherman Pass Road No. 22S05. · Tulare, California

The project would provide ecological restoration by reducing fuels loading through removal of dead or damaged trees and by prescribed burning. It would also remove hazard trees from public roadways In the Sirretta Road/Sherman Pass area

Vegetation management (other than forest products)Fuels managementForest products
Scoping Start
08/08/2011
Decision
12/2011 (Estimated)
Implementation
04/2012 (Estimated)
Project documents
Penelope Shibley · pshibley@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (13), 36 Cfr 220.6(E)(13)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityLand Use Adjustments; Boundary Adjustments; Harzardous Waste Compliance Actions; Facility Improvements/Construction; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Special Use Authorizations; Land Purchases; Facility Maintenance; Abandoned Mine Land Clean-Up; Minerals Or Geology Plans Of Operations; Special Products Sales; Noxious Weed Treatments; Land Exchanges; Road Maintenance; Road Improvements/Construction; Rangeland Vegetation Improvements; Timber Sales (Salvage); Watershed Improvements
Decision Memo Sirretta Road Blowdown SalvageDecision Signed Date: 12/15/2011
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSec. 13 & 24, T22S, R33E and Sec. 19 & 20, T22S, R34E MDBM;
Environmental Impact Statement · Kern River Ranger District · updated 8/1/2019
Northern half of the Piute Mountains, located approximately seven (7) air miles southeast of Lake Isabella, CA. · Kern, California

Consists of salvage/harvest of fire killed/damaged trees; mechanically treating areas of densely stocked fire killed trees; restoring meadow habitat and mitigate erosion at French Meadow; and reconstructing existing roads to access treatment areas.

Watershed managementForest productsVegetation management (other than forest products)Fuels managementWildlife, fish, rare plants
NOI in Federal Register
01/22/2009
DEIS NOA in Federal Register
11/06/2009
FEIS NOA in Federal Register
04/30/2010
Decision
04/2010 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
Steve Anderson · swanderson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels); Species Habitat Improvements; Road Maintenance; Road Improvements/Construction; Timber Sales (Salvage); Watershed Improvements
Piute Fire Restoration ProjectDecision Signed Date: 04/16/2010 Legal Notice Date: 04/30/2010
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT.27-29S., R.33-34E., MDM.
Environmental Assessment · Kern River Ranger District · updated 8/1/2019
Northern half of the Piute Mountains, located approximately seven (7) air miles southeast of Lake Isabella, CA. · Kern, California

Commercial timber sale to remove hazard trees for safety purposes along approximately 32 miles of roads affected by the 2008 Piute Fire.

Forest productsRoad management
Scoping Start
11/19/2008
Comment Period
03/13/2009
Decision
05/2009 (Estimated)
Implementation
05/2009 (Estimated)
Project documents
Andrew Orlemann · aorlemann@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Maintenance; Timber Sales (Salvage)
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSecs. 11, 13-14, 22-26, & 36, T.28S., R.33E.; Secs. 8-9, 16-20, & 29-32, T.28S., R.34E.; and Sec. 6, T.29S., R.34E., MDM.
Environmental Assessment · Hume Lake Ranger District · updated 8/1/2019
Sampson Allotment lies between Pine Ridge and Verplank Ridge, north of McKenzie Ridge to the Kings River. · Fresno, California

Proposed project to renew a grazing permit on the Sampson Allotment, which includes areas inside and outside of Giant Sequoia National Monument and the Kings River Special Management Area.

Special area managementGrazing managementSpecial use management
Scoping Start
04/30/2010
Comment Period
05/30/2012
Decision
08/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Special AuthorityGrazing, Rescissions Act Of 1995
Notice and Comment Regulation215
Project ActivityGrazing Allotment Management; Grazing Authorizations; Special Use Authorizations
Sampson Grazing Allotment Renewal ProjectDecision Signed Date: 08/03/2012 Legal Notice Date: 08/07/2012
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT12-13S, R26-27E, MDB&M
Environmental Impact Statement · Western Divide Ranger District · updated 8/1/2019
Project area is adjacent to the Forest Service/Tule River Indian Reservation boundary. · Tulare, California

This project will reduce flammable vegetation through prescribed burning within the area adjoining the northern boundary of the Tule River Indian Reservation. Proposed under the Tribal Forest Protection Act.

Fuels management
NOI in Federal Register
08/26/2008
DEIS NOA in Federal Register
04/25/2014
FEIS NOA in Federal Register
08/08/2014
Decision
01/2015 (Estimated)
Implementation
06/2015 (Estimated)
Project documents
Richard Stevens · ristevens@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels)
Tule River Reservation Protection Project Record of DecisionDecision Signed Date: 01/29/2015
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionSections 4-10, T.21S., R.31E., and Section 1, 2, 11-14, T.21S., R.30E., MDM.
Environmental Assessment · Kern River Ranger District · updated 7/30/2019
Breckenridge Mountain, Kern County, California, approx 11 miles SW of Lake Isabella, California · Kern, California

Variably thin approx 892 acres in WUI defense & threat zones using mechanical and/or hand thinning methods. Material may be sold as commercial sawlogs. Excess surface fuels will be treat by piling/burning, underburning or chipping.

Forest productsFuels managementVegetation management (other than forest products)
Scoping Start
10/27/2010
Objection Period Start
05/07/2012
Decision
08/2012 (Estimated)
Implementation
09/2012 (Estimated)
Project documents
Brian Bergman · brianbergman@fs.fed.us
NEPA / regulatory detail
Special AuthorityHfra Title I: Municipal Watersheds
Notice and Comment Regulation218
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green)
Breckenridge Forest Health and Fuels Reduction Project DN & FONSIDecision Signed Date: 08/01/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT28S, R32E, Sections 19, 20, 30; T28S, R31E, Sections 14,15, 21-27, 34-36 MDB&M
Environmental Assessment · Kern River Ranger District · updated 7/30/2019
Approximately 11 miles southwest of Lake Isabella in the Breckenridge Mountains. · Kern, California

Variably thin 998 acres of plantations using hand thinning methods. Excess surface fuels will be treated by chipping and/or lop & scatter (with broadcast burning), hand piling & burning, or made available for personal use firewood.

Fuels managementVegetation management (other than forest products)
Scoping Start
12/09/2009
Objection Period Start
05/04/2011
Decision
07/2011 (Estimated)
Implementation
06/2011 (Estimated)
Project documents
John Gomez · johngomez@fs.fed.us
NEPA / regulatory detail
Special AuthorityHfra Title I: Wildland-Urban Interface
Notice and Comment Regulation218
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
Breckenridge Plantation ThinningDecision Signed Date: 07/18/2011
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT28S, R31-32E, MDB&M
Environmental Assessment · Kern River Ranger District · updated 7/30/2019
Kern Plateau - Trout Creek, Rattlesnake Creek and Dark Canyon subwatershed of the Kern River Ranger District. Along portions of Forest Service roads 22S20 and 22S38. · Tulare, California

Salvage of 130 acres of fire and insect killed trees, with less than 0.5 miles of temporary road construction. Approximately 145 acres will be planted. Retain snag retention corridor consisting of 68 acres. (See "other project information" below.)

Forest productsRoad managementFuels managementVegetation management (other than forest products)
Scoping Start
02/01/2008
Comment Period
02/13/2009
Decision
04/2009 (Estimated)
Implementation
05/2009 (Estimated)
Project documents
Brian Bergman · brianbergman@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityForest Vegetation Improvements; Road Maintenance; Timber Sales (Salvage)
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSections16, 17, 20, & 21, T.22S., R.34E., MDM. Approximately 17 air miles north/northeast of Kernville, CA.
Decision Memo · Hume Lake Ranger District · updated 7/19/2019
Location is Eshom portion of HL District from highway 245 east to NPS boundary and Dark Canyon Rd (14S43) south to SQF Forest boundary with private lands. · Fresno; Tulare, California

Improve forest health & wildlife habitat in high intensity drought/insect-kill area using mastication, biomass removal, prescribed burning, road decommissioning & reforestation in Eshom and Dry creek drainages. Reduces fuels near private property.

Watershed managementVegetation management (other than forest products)Road managementFuels managementForest productsWildlife, fish, rare plants
Scoping Start
09/07/2018
Decision
07/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (20), 36 Cfr 220.6(E)(20)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Salvage)
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT14-15S, R27-28E, MDB&M
Environmental Assessment · Sequoia National Forest All Units · updated 7/3/2019
The four WDRD meadows occur in the headwaters of the North Fork of the Kern River, west side of the river. The six KRRD meadows occur in the South Fork of the Kern River headwaters. · Tulare, California

This project addresses watershed improvement in three meadows (Upper Parker, Lower Parker, Packsaddle) on Western Divide RD and five meadows (Little Horse, Powell, Granite Knob, Little Troy, Troy) on Kern River RD.

Watershed management
Scoping Start
07/13/2017
Comment Period
11/16/2018
Objection Period Start
03/01/2019
Decision
04/2019 (Estimated)
Implementation
08/2019 (Estimated)
Project documents
Nina Hemphill · nphemphill@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityWatershed Improvements
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District; Kern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 6/28/2019
Hobo Campground, lower Kern River and Tillie Creek Campground, Isabella Lake near Wofford Heights · Kern, California

Storm damage repairs to road crossings at creeks in Hobo and Tillie Creek Campgrounds

Road management
Scoping Start
04/12/2019
Decision
06/2019 (Estimated)
Implementation
07/2019 (Estimated)
Project documents
Penelope Shibley · PENELOPE.SHIBLEY@USDA.GOV
NEPA / regulatory detail
Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18); 32.2 (19), 36 Cfr 220.6(E)(19)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Improvements/Construction
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 6/6/2019
near French Gulch at Isabella Lake on the Kern River Ranger District of the Sequoia National Forest · Kern, California

Special Use Permit issuance for a museum/visitor center, preserving, restoring and teaching Native American culture, history and traditions.

Special use management
Scoping Start
04/05/2019
Comment Period
04/05/2019
Decision
06/2019 (Estimated)
Implementation
06/2019 (Estimated)
Project documents
Joseph Martin · josephmartin@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
KERN RIVER PAIUTE COUNCIL, NUUI CUNNI NATIVE AMERICAN CULTURAL CENTER SUPDecision Signed Date: 06/05/2019
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNW 1/4Section 19, T.26S., R.33E., MDBM
Decision Memo · Sequoia National Forest All Units · updated 3/20/2019
Linear existing lines within the Sequoia National Forest · Kern; Tulare, California

Approve continued operations, maintenance and use of existing distribution and transmission power lines and infrastructure for Southern California Edison & Pacific Gas & Electric located within designated corridors in the Sequoia National Forest.

Special use management
Scoping Start
03/21/2018
Decision
02/2019 (Estimated)
Implementation
03/2019 (Estimated)
Project documents
Spencer Bleadorn · sbleadorn@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityElectric Transmission
ForestsSequoia National Forest
DistrictsSequoia National Forest All Units
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 3/4/2019
Project is located off of Breckenridge Lookout Road (28S07) adjoining the Breckenridge Mountain Communications Site, northeast of Bakersfield. · Kern, California

Removal of approximately 65 trees on 50 acres which are causing interference with a microwave communications site

Special use managementForest products
Scoping Start
02/06/2015
Decision
03/2015 (Estimated)
Implementation
03/2015 (Estimated)
Project documents
Brian Block · brianblock@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (12), 36 Cfr 220.6(E)(12)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTimber Sales (Green)
SCE Microwave Tree Removal ProjectDecision Signed Date: 02/23/2015
Decision Memo (Corrected) SCE Microwave Tree RemovalDecision Signed Date: 03/10/2015
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNE 1/4 Section 36, T28S, R31E, MDB&M
Decision Memo · Kern River Ranger District · updated 2/20/2019
Isabella Lake and the Upper Kern River · Kern; Tulare, California

Issue one- to five-year special use permits to groups to hold recreational fishing events.

Special use management
Scoping Start
06/26/2018
Decision
02/2019 (Estimated)
Implementation
03/2019 (Estimated)
Project documents
Tricia Maki · triciamaki@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 2/14/2019
Kern River, Kern Plateau, Isabella Lake, Western Divide · Kern; Tulare, California

Renew five expiring special use permits for whitewater and mountaineering outfitter guides for a 10-year period.

Special use management
Scoping Start
11/16/2018
Decision
02/2019 (Estimated)
Implementation
02/2019 (Estimated)
Project documents
Tricia Maki · triciamaki@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District; Kern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Hume Lake Ranger District · updated 11/26/2018
Log Corral Meadow area north toward Huckleberry Meadow along Grant Grove peninsula of Kings Canyon National Park. · Fresno; Tulare, California

Coordinate with neighboring Kings Canyon National Park to prescribe burn an estimated 511 acres of NFS land, while they burn an estimated 1,126 acres on NPS land in the next decade.

Fuels management
Scoping Start
03/19/2018
Decision
11/2018 (Estimated)
Implementation
12/2018 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels)
PAN, PARK RIDGE, Tower PRESCRIBED FireSDecision Signed Date: 11/26/2018
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13-14S, R28E
Decision Memo · Kern River Ranger District · updated 11/23/2018
Alta Sierra Ski area at Shirley Meadow · Kern, California

Issue a new 40 year permit with no changes from the current 20 year permit or master development plan.

Special use management
Scoping Start
04/2014 (Estimated)
Decision
06/2014 (Estimated)
Implementation
07/2014 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (9), 36 Cfr 220.6(D)(9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionShirley Meadows T25S, R32E, Section 32
Decision Memo · Kern River Ranger District · updated 11/23/2018
Various locations on the Western Divide and Kern River Ranger Districts · Kern; Tulare, California

Issuance of a one year outfitter guide special use permit-- teaching a hybrid of Native American traditions & contemporary backpacking/wilderness survival skills.

Special use management
Scoping Start
07/16/2010
Decision
12/2013 (Estimated)
Implementation
12/2013 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (8), 36 Cfr 220.6(D)(8)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District; Kern River Ranger District
Legal Land DescriptionT20-28S, R30-34E, MDB&M
Decision Memo · Kern River Ranger District · updated 10/25/2018
Kern Plateau between Pine Flat and Big Meadow T23S & T24S, R34E · Tulare, California

Construct new motorized trail sections that bypass the existing non-motorized sections of the Cannell Meadow National Recreation Trail (33E32).

Recreation management
Scoping Start
04/18/2018
Decision
10/2018 (Estimated)
Implementation
11/2018 (Estimated)
Project documents
Tricia Maki · triciamaki@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management; Travel Management
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Hume Lake Ranger District · updated 10/18/2018
Stony Creek Lodge special use permit site on Generals Highway. · Tulare, California

Expand lodging facilities to 45 rooms at the Stony Creek Lodge, on Generals Highway.

Recreation managementHeritage resource managementFacility managementSpecial use management
Scoping Start
09/22/2003
Comment Period
07/26/2004
Decision
10/2013 (Estimated)
Implementation
07/2014 (Estimated)
Project documents
Carol Hallacy · challacy@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDeveloped Site Management; Facility Improvements/Construction; Heritage Resource Management; Special Use Authorizations
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionSection 33, T.14S., R.29E., MDM. < 5 acres.
Environmental Assessment · Kern River Ranger District · updated 9/21/2018
Improve river access at the whitewater boating sites on the Upper Kern River run and the Lower Kern River run. (See Other Information block.) · Kern, California

Improve river access on the Upper Kern River at Road's End & Camp 3, and add permanent vault toilets at Riverkern Beach, Camp 3, Thunderbird, Road's End, and Willow Point. Improve river access on Lower Kern River, at Democrat Raft Take-Out.

Recreation management
Scoping Start
02/20/2009
Comment Period
09/22/2009
Decision
11/2009 (Estimated)
Implementation
01/2010 (Estimated)
Project documents
Cheryl Bauer · cabauer@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDeveloped Site Management; Facility Improvements/Construction; Dispersed Recreation Mgmt.
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT.24S., R.33E., Sec. 4 (Riverkern Beach), Sec. 29 (Camp 3) & Sec. 30 (Thunderbird); T.23S., R.33E., Sec. 11 (Road's End) & Sec. 1 (Willow Point); & T.27S., R.31E., Sec. 5 (Democrat Raft Take-Out).
Decision Memo · Kern River Ranger District · updated 9/21/2018
Nine sites: Halfway, Thunderbird, Chico Flat, Corral Creek, Springhill, Old Goldledge, Ant Canyon, Lower and Upper Chamise, Calkins Flat · Tulare, California

Project would implement both road maintenance & site rehabilitation work identified within nine dispersed recreation areas located in the Upper Kern Canyon. All nine site accommodate both day use and overnight camping.

Road managementRecreation management
Scoping Start
12/31/2009
Decision
05/2010 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
Cheryl Bauer · cabauer@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDispersed Recreation Mgmt.; Travel Management
Upper Kern Canyon Legacy Roads ProjectDecision Signed Date: 05/05/2010
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSections 6, 8, 19, 30-31, T24S, R33E; Sections 31, 25, 23, T23S, R33E; MDB&M
Decision Memo · Hume Lake Ranger District · updated 8/9/2018
In Eshom Creek adjacent to Eshom Campground, camp site number 18. · Tulare, California

Stabilize streambank eroding part of Eshom Campground site 18 and depositing sediment into Eshom Creek, rehab riparian area being eroded.

Wildlife, fish, rare plantsWatershed managementRecreation management
Scoping Start
03/05/2018
Decision
08/2018 (Estimated)
Implementation
10/2018 (Estimated)
Project documents
Don Kozlowski · dkozlowski@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityDeveloped Site Management; Species Habitat Improvements; Watershed Improvements
ESHOM CAMPGROUND SITE 18 Bank StabilizationDecision Signed Date: 08/08/2018
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT14S, R28E, Sec.20
Decision Memo · Kern River Ranger District · updated 8/7/2018
Allotments are located in the northern portion of the Scodie Mountains, entirely within the Kiavah Wilderness, on the Kern River Ranger District. · Kern, California

Reauthorize livestock grazing under current management for two (2) allotments in the Kiavah Wilderness.

Grazing management
Scoping Start
05/25/2007
Comment Period
09/26/2007
Decision
10/2007 (Estimated)
Implementation
11/2007 (Estimated)
Project documents
Susan Porter · smporter@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityGrazing, Rescissions Act Of 1995
Notice and Comment Regulation215
Project ActivityGrazing Authorizations
SCODIE MOUNTAIN NORTH GRAZING ALLOTMENTSDecision Signed Date: 09/26/2007 (FS Withdrawn) Legal Notice Date: 09/26/2007
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT.27-26S., R35-37E., MDM. Approximately 27,597 acres. (Primary use = 808 acres; Secondary use = 246 acres; and Incidental use = 26,543 acres.
Decision Memo · Kern River Ranger District · updated 8/6/2018
San Mateo Mine, Delonegha Prospect, Deep Creek Cave · Kern; Tulare, California

Mitigate threats by restricting access at two historic mines and a cave

Wildlife, fish, rare plantsMinerals and geology
Scoping Start
06/25/2018
Decision
08/2018 (Estimated)
Implementation
10/2018 (Estimated)
Project documents
Tim Kelly · tkelly@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (5), 36 Cfr 220.6(D)(5); 32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction; Species Habitat Improvements; Heritage Resource Management; Facility Maintenance; Abandoned Mine Land Clean-Up
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Western Divide Ranger District · updated 8/3/2018
Greenhorn Mountain area. · Kern, California

Analysis to determine changes to allotment management plans.

Grazing management
Scoping Start
07/23/2004
Comment Period
09/19/2006
Decision
09/2006 (Estimated)
Implementation
11/2006 (Estimated)
Project documents
Chris Sanders · csanders@fs.fed.us
NEPA / regulatory detail
Special AuthorityGrazing, Rescissions Act Of 1995
Notice and Comment Regulation215
Project ActivityGrazing Allotment Management
GREENHORN RANGE GRAZINGDecision Signed Date: 09/18/2006 Legal Notice Date: 09/19/2006
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionDistrictwide. T.24, 25, 26, 27, 28S., R.31E., MDM. 22,000 acres.
Environmental Assessment · Kern River Ranger District · updated 8/2/2018
Breckenridge Mountain on the Kern River Ranger District. · Kern, California

Reissue livestock grazing permits under current management for four (4) allotments: Breckenridge, Pechacho, Hobo, and Cow Flat.

Grazing management
Scoping Start
04/19/2011
Comment Period
07/12/2011
Decision
09/2011 (Estimated)
Implementation
10/2011 (Estimated)
Project documents
Mark Stieler · mstieler@fs.fed.us
NEPA / regulatory detail
Special AuthorityGrazing, Rescissions Act Of 1995
Notice and Comment Regulation215
Project ActivityGrazing Allotment Management; Grazing Authorizations; Grazing Structural Improvements
Breckenridge Mountain Grazing Project Decision NoticeDecision Signed Date: 09/29/2011 Legal Notice Date: 09/29/2011
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT.27-28S., R.30-32 E., MDM. Approximately 39,963 acres (Breckenridge, 11,883 ac; Pechacho, 5,315 ac; Hobo, 4,749 ac; & Cow Flat, 18,016 ac.)
Decision Memo · Kern River Ranger District · updated 8/2/2018
The allotments are located in the Piute Mountains, on the Kern River Ranger District. · Kern, California

Reauthorize livestock grazing permit under current management for five (5) allotments.

Grazing management
Scoping Start
07/06/2007
Decision
09/2008 (Estimated)
Implementation
10/2008 (Estimated)
Project documents
Susan Porter · smporter@fs.fed.us
NEPA / regulatory detail
Categorical ExclusionSec 339
Special AuthorityGrazing, Sec 339, 2005 Consolidated Appropriations Bill (Grazing Authorizations On An Allotment)
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Authorizations
Piute Mountains Grazing ProjectDecision Signed Date: 09/29/2008
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT.27-28S., R.33-34E., MDM. Approximately 82,484 acres. (Primary use = 2,292 acres; Secondary use = 4,372 acres; and Incidental use = 69,669 acres.
Environmental Assessment · Western Divide Ranger District · updated 7/20/2018
Tule River Hydroelectric Powerhouse, Adm Bldgs, Switchyard, Camp 4 Rd,ROWs-Tunnel Trail, Penstock Trail, Redwood Penstock, Adit Road, Surge Tank Road, · Tulare, California

This project is a maintenance program involving the use of herbicides to control vegetation around hydropower facilities, access roads and trails.

Facility management
Scoping Start
07/05/2013
Comment Period
07/05/2013
Objection Period Start
01/2018 (Estimated)
Decision
02/2018 (Estimated)
Implementation
05/2018 (Estimated)
Project documents
Chris Sanders · csanders@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFacility Maintenance
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 7/6/2018
Taylor Meadow, Kern Plateau · Tulare, California

Install erosion control in a gully of Taylor Meadow

Watershed management
Scoping Start
04/23/2013
Decision
07/2018 (Estimated)
Implementation
07/2018 (Estimated)
Project documents
Keith Stone · kstone@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7); 32.2 (19), 36 Cfr 220.6(E)(19)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 5/16/2018
Sherman Pass Road at Fish Creek crossing · Tulare, California

Replace undersized culvert along Sherman Pass Road at Fish Creek

Road managementWatershed managementWildlife, fish, rare plants
Scoping Start
08/11/2014
Decision
09/2014 (Estimated)
Implementation
10/2015 (Estimated)
Project documents
Steve Anderson · swanderson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityHarzardous Waste Compliance Actions; Species Habitat Improvements; Road Improvements/Construction; Watershed Improvements
Fish Creek Aquatic Organism Passage RestorationDecision Signed Date: 09/30/2014
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT.21S., R.35E., Sections 32 &amp; 29, MDB&amp;M.
Decision Memo · Hume Lake Ranger District · updated 5/2/2018
T14-15S,R27-28E, MDB&M · Fresno; Tulare, California

Maintain up to 769 acres on 6 existing fuelbreaks in the Eshom portion of the district. Proposed treatments are hand and machine felling hazard trees and piling the material. Piles would be burned.

Fuels management
Scoping Start
06/05/2017
Decision
05/2018 (Estimated)
Implementation
06/2018 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels)
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 3/19/2018
On the Kern River near Miracle Hot Springs Day Use Area, adjacent to Hobo Campground off the Old Kern Canyon Road (214). · Kern, California

Renewal of expired special use permit for a 5-year term for the use of the Miracle Hot Springs Day Use Area for teaching and kayak events.

Special use managementRecreation management
Scoping Start
02/22/2018
Decision
03/2018 (Estimated)
Implementation
03/2018 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
DECISION MEMO KERN VALLEY RIVER COUNCIL SPECIAL USE PERMITDecision Signed Date: 03/16/2018
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSection 15, T.27S., R.32E. MDBM
Decision Memo · Kern River Ranger District · updated 2/23/2018
T25-28S, R31-33E MDBM · Kern, California

Renew special use permits for 16 roads and 2 research sites with roads

ResearchSpecial use management
Scoping Start
11/27/2017
Decision
02/2018 (Estimated)
Implementation
02/2018 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 2/23/2018
Sec. 20 and 29, T25S, R32E, MDBM, Summit Recreational Residence Tract off Highway 155 and Windy Gap Road (25S17). · Kern, California

Issue a permit for a 20-year period for existing roads and water system, including replacement of water tanks to serve existing cabins.

Special use management
Scoping Start
12/18/2017
Decision
02/2018 (Estimated)
Implementation
02/2018 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 2/5/2018
Breckenridge Mountain · Kern, California

Remove dead and dying trees near homes and roads, reduce fuels buildup

Vegetation management (other than forest products)Fuels managementForest products
Scoping Start
10/02/2017
Decision
02/2018 (Estimated)
Implementation
09/2018 (Estimated)
Project documents
Keith Stone · kstone@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (13), 36 Cfr 220.6(E)(13)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityBoundary Adjustments; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Road Maintenance; Timber Sales (Salvage)
LUCAS CREEK PROJECT DECISION MEMODecision Signed Date: 02/05/2018
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Sequoia National Forest All Units · updated 12/18/2017
Multiple locations · Kern; Tulare, California

Renewal of multiple communication leases and permits at 33 existing sites on the Sequoia National Forest.

Special use management
Scoping Start
10/13/2016
Decision
11/2017 (Estimated)
Implementation
12/2017 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsSequoia National Forest All Units
Legal Land DescriptionNot Applicable
Environmental Assessment · Kern River Ranger District · updated 12/18/2017
Highway 178 in the Lower Kern Canyon near Forest Service Road 28S68 · Kern, California

New communications use lease at an existing communications site.

Special use management
Scoping Start
08/2016 (Estimated)
Comment Period
08/2016 (Estimated)
Objection Period Start
01/2017 (Estimated)
Decision
03/2017 (Estimated)
Implementation
04/2017 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land Description.5 (one half) acre. Section 5, T28S, R31E, MDBM; elevation 2,300 ft.
Decision Memo · Western Divide Ranger District · updated 9/27/2017
The proposed location for this facility is adjacent to Bear Creek Road, Mile marker 220 · Tulare, California

Construct a new permanent corral measuring 60 feet by 80 feet with two short wing fences extending no more than 100 feet from the corral. This livestock handling facility will be used during turn out and gathering of livestock.

Grazing management
Scoping Start
06/01/2017
Decision
08/2017 (Estimated)
Implementation
08/2017 (Estimated)
Project documents
Joe Loehner · jloehner@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (9), 36 Cfr 220.6(E)(9)
Special AuthorityGrazing, Rescissions Act Of 1995
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Allotment Management; Grazing Structural Improvements
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionT 20 S, R 30 E, Section 9, Mount Diablo Base and Meridian.
Environmental Assessment · Western Divide Ranger District · updated 9/25/2017
The project location is north of HWY 190 and between Wishon Campground and the Sequoia Crest community. · Tulare, California

Reduce fuels in and around the Wishon Campground, around Doyle Springs and Sequoia Crest communities, along FR 20S03, and within the Alder Creek Grove. All proposed activities are on Forest Service land.

Vegetation management (other than forest products)Road managementFuels management
Scoping Start
04/11/2016
Comment Period
10/2017 (Estimated)
Objection Period Start
11/2017 (Estimated)
Decision
01/2018 (Estimated)
Implementation
04/2018 (Estimated)
Project documents
David Ernst · dernst@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 7/20/2017
Piute Mountains · Kern, California

Install a bat gate and a road gate to restrict access to underground mine.

Wildlife, fish, rare plantsMinerals and geologyRoad management
Scoping Start
06/12/2017
Decision
07/2017 (Estimated)
Implementation
07/2017 (Estimated)
Project documents
Tim Kelly · tkelly@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6); 32.2 (20), 36 Cfr 220.6(E)(20)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Allotment Management
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Hume Lake Ranger District · updated 7/20/2017
In Tenmile subwatershed, along Tenmile Road (FR 13S09). · Fresno; Tulare, California

Fell the conifers competing with aspen in 5 stands by hand thinning. Each stand is unique, but cumulatively approximately 120 small (less than 16" dbh)cedars and firs would be cut. Small material piled and burned/chipped, large material left on site.

Wildlife, fish, rare plantsVegetation management (other than forest products)
Scoping Start
05/26/2015
Decision
07/2017 (Estimated)
Implementation
08/2017 (Estimated)
Project documents
Jeff Cordes · jcordes@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements; Species Habitat Improvements
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13-14S, R28E, MDB&M
Environmental Assessment · Kern River Ranger District · updated 7/19/2017
Located in the Alaska Flat area of the Piute Mountains, on Kern River Ranger District. · Kern, California

Closure of mine openings and removal of structures, old equipment, and trash, from nine (9) abandoned mines.

Wildlife, fish, rare plantsMinerals and geologyWatershed management
Scoping Start
10/09/2008
Project documents
Tim Kelly · tkelly@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Species Habitat Improvements; Abandoned Mine Land Clean-Up
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSections 17, 18, 19, & 20, T.28S., R.34E., MDM. Kern County, CA.
Decision Memo · Kern River Ranger District · updated 7/18/2017
Kern Plateau near Osa Meadow · Tulare, California

Improve East Beach Creek Road (20S25) to reduce erosion and decommission three non-system spur roads near Osa Meadow.

Road managementWildlife, fish, rare plantsWatershed management
Scoping Start
05/02/2017
Decision
05/2017 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
Keith Stone · kstone@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); 32.2 (20), 36 Cfr 220.6(E)(20)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityHarzardous Waste Compliance Actions; Species Habitat Improvements; Road Improvements/Construction; Watershed Improvements
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Hume Lake Ranger District · updated 7/18/2017
Mill Flat Creek drainage · Fresno, California

A proposal to seasonally close the Davis Road (FR 12S01) (approximately 12/1 - 4/15 based on weather conditions) and to decommission 13 forest roads or portions of roads (a total of 3.3 miles) within the Mill Flat Creek Critical Aquatic Refuge.

Wildlife, fish, rare plantsWatershed managementRoad management
Scoping Start
02/17/2012
Comment Period
01/19/2017
Objection Period Start
03/01/2017
Decision
04/2017 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
Jeff Cordes · jcordes@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Decommissioning; Species Habitat Improvements; Road Maintenance; Travel Management; Watershed Improvements
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13S, R26-27E MDB&M
Decision Memo · Hume Lake Ranger District · updated 7/18/2017
Communities of Pinehurst and Neff's Camp · Fresno, California

Fuel reduction on 260 acres around Pinehurst and Neff's Camp communities via tree and shrub cutting and pruning, then chipping, or piling and burning the material. Proposal in mutual fire response area of CalFire (187 ac) and Forest Service (73 ac)

Fuels management
Scoping Start
07/12/2016
Decision
05/2017 (Estimated)
Implementation
06/2017 (Estimated)
Project documents
Brian Vasquez · bvasquez@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels)
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionSections 13, 14, 23, & 24, T.12S., R.24E., MDB&M
Environmental Assessment · Kern River Ranger District · updated 6/30/2017
Isabella Lake (Hanning Flat, Stine Cove, Robinson Cove, Rocky Point, Camp 9, Wofford Heights, Tillie Creek, Joughin Cove, Kissack Bay and other areas as needed · Kern; Tulare, California

Treat 1500 acres of tamarisk (salt cedar) an invasive plant at Isabella Lake, using mechanical treatments or herbicides where necessary.

Watershed managementVegetation management (other than forest products)
Scoping Start
03/17/2015
Comment Period
09/2017 (Estimated)
Objection Period Start
10/2017 (Estimated)
Decision
10/2017 (Estimated)
Implementation
11/2017 (Estimated)
Project documents
Steve Anderson · swanderson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityWatershed Improvements
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionTownships 25 and 26 S, Range 33 and 34 E, MDBM
Environmental Assessment · Kern River Ranger District · updated 6/29/2017
Black Gulch South, dispersed area offering overnight and day use opportunities, and access to Kern River. Sandy Flat Day Use Area, approximately 44 mi NE of Bakersfield along old Kern Canyon Road · Kern, California

Reconstruct approximately 0.75 miles of the Black Gulch South Road, build permanent toilet facilities, and dumpster pads will be added to this site. Sandy Flat Day Use Area, construct asphalt surface trail from parking lot to Kern River

Recreation managementRoad management
Scoping Start
10/26/2011
Comment Period
03/06/2013
Objection Period Start
01/31/2017
Decision
03/2017 (Estimated)
Implementation
03/2017 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityRoad Maintenance
DN/FONSI for the Borel Relicensing Recreation Enhancement ProjectDecision Signed Date: 08/13/2013 Legal Notice Date: 08/16/2013
NEW DN AND FONSI FOR THE BOREL RELICENSING RECREATION ENHANCEMENT PROJECTDecision Signed Date: 03/30/2017
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionBlack Gulch South: Section 10, T27S, R32E; Sandy Flat Day Use: Section 15, T27S, R32E, MDB&M
Decision Memo · Kern River Ranger District · updated 6/29/2017
Piute Mountains near Weldon Meadow · Kern, California

Mitigate threats to wildlife by restricting access to underground mine

Minerals and geologyWildlife, fish, rare plants
Scoping Start
09/09/2016
Decision
09/2016 (Estimated)
Implementation
09/2016 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Allotment Management
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 3/29/2017
Isabella Lake · Kern, California

Issue a 5-year temporary special use permit to hold fishing derbies on Isabella Lake.

Special use management
Scoping Start
02/01/2017
Decision
03/2017 (Estimated)
Implementation
04/2017 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Sequoia National Forest All Units · updated 2/14/2017
Existing trails · Kern; Tulare, California

Outfitter works with 8th, 10th, 11th, and 12th grade students in small groups teaching hiking, rock climbing, backpacking and camping.

Recreation managementSpecial use management
Scoping Start
10/31/2016
Decision
02/2017 (Estimated)
Implementation
02/2017 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
CHADWICK OUTDOOR EDUCATION SCHOOL OUTFITTER GUIDE SPECIAL USE PERMITDecision Signed Date: 02/13/2017
ForestsSequoia National Forest
DistrictsSequoia National Forest All Units
Legal Land DescriptionNot Applicable
Environmental Impact Statement · Kern River Ranger District · updated 1/31/2017
Surrounding the community of Alta Sierra in Kern County · Kern, California

Provide defensible space around the community of Alta Sierra and nearby structures, improve forest health and provide for ecological restoration.

Forest productsFuels management
NOI in Federal Register
09/16/2015
DEIS NOA in Federal Register
04/2016 (Estimated)
FEIS NOA in Federal Register
06/2016 (Estimated)
Objection Period Start
06/2016 (Estimated)
Decision
08/2016 (Estimated)
Implementation
09/2016 (Estimated)
Project documents
Steve Anderson · swanderson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green)
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionTownship 25 South Range 32 East, MDB&M
Decision Memo · Kern River Ranger District · updated 1/23/2017
Greenhorn Mountains, S 21, T 25 S, R 32 E, 10936 Elm Drive, Alta Sierra · Kern, California

Re-issue a temporary SUP for a septic system encroaching on forest land

Special use management
Scoping Start
09/01/2016
Decision
01/2017 (Estimated)
Implementation
01/2017 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
JIM THOMSEN SEPTIC SYSTEM ENCROACHMENT 5-YEAR SPECIAL USE PERMITDecision Signed Date: 01/18/2017
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 11/18/2016
Near Grouse Meadow in the Piute Mountains · Tulare, California

Renew a special use permit for unimproved dirt road (approximately 105 feet long and 20 feet wide for 0.05 acres) that accesses private property from Gallup Road (FS Road 29S03) near Grouse Meadow in the Piute Mountains.

Special use management
Scoping Start
09/01/2016
Decision
11/2016 (Estimated)
Implementation
11/2016 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Environmental Impact Statement · Western Divide Ranger District · updated 9/30/2016
Greenhorn Mountains adjoining Sugarloaf Road (24S15) between Alta Sierra (Portuguese Pass) and Dunlap Pass, south of Johnsondale · Tulare, California

Ecological restoration, by thinning and prescribed burning, to restore a healthy, diverse, fire-resistant forest structure and species composition.

Forest productsWatershed managementVegetation management (other than forest products)Fuels management
NOI in Federal Register
01/30/2015
DEIS NOA in Federal Register
04/08/2016
FEIS NOA in Federal Register
07/2016 (Estimated)
Objection Period Start
07/2016 (Estimated)
Decision
09/2016 (Estimated)
Implementation
10/2016 (Estimated)
Project documents
ODell Tucker · otucker@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green); Watershed Improvements
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land Description11,000 acres within T24S, R32E, MDB&M
Environmental Assessment · Kern River Ranger District · updated 5/26/2016
Sections 4, 9, and 10, T. 22S, R. 34 E__ · Tulare, California

Sampling and exploration of ore from an existing barite mine.

Minerals and geology
Scoping Start
04/29/2014
Comment Period
02/09/2016
Objection Period Start
03/30/2016
Decision
05/2016 (Estimated)
Implementation
05/2016 (Estimated)
Project documents
Tim Kelly · tkelly@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityHarzardous Waste Compliance Actions; Minerals Or Geology Plans Of Operations; Road Maintenance
Decision Notice and FONSI, LA PALOMA #1 AND # 2 MINING PLAN OF OPERATIONSDecision Signed Date: 05/26/2016
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Environmental Assessment · Hume Lake Ranger District · updated 4/26/2016
Millwood Staging Area is a popular OHV use site, split by the Mill Flat Creek which is a critical aquatic refuge, & overlaps the potentially historic town site of Millwood · Fresno, California

Proposal to redesign the Millwood OHV Staging Area to better define camp/day use areas and road access in order to reduce impacts to the creek and other resources.

Recreation managementWatershed managementSpecial use managementRoad managementHeritage resource managementWildlife, fish, rare plants
Scoping Start
05/24/2010
Comment Period
03/08/2016
Decision
04/2016 (Estimated)
Implementation
06/2016 (Estimated)
Project documents
Carol Hallacy · challacy@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityDeveloped Site Management
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13-14S, R27E, MDB&M
Decision Memo · Hume Lake Ranger District · updated 3/30/2016
Upper reaches of Mill Flat Creek drainage between 4,500 and 6,000 feet in elevation. · Fresno, California

The Rough Fire Initial Reforestation Project proposes to plant up to 500 acres with a mix of sugar and ponderosa pine in the Mill Flat Creek drainage where the Rough Fire burned at high severity.

Vegetation management (other than forest products)
Scoping Start
02/05/2016
Decision
03/2016 (Estimated)
Implementation
03/2016 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (5), 36 Cfr 220.6(E)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements
Rough Fire Initial PlantingDecision Signed Date: 03/29/2016
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13-14S, R27E, MDB&M
TRAVEL MANAGEMENT Completed
Environmental Impact Statement · Sequoia National Forest All Units · updated 3/30/2016
Tule River/Hot Springs Ranger District outside the boundaries of the Giant Sequoia National Monument and portions of the Kern River Ranger District. · Kern; Tulare, California

Designate a system of routes available to motorized vehicles in portions of the Kern River Ranger District and Western Divide Ranger District outside of the Giant Sequoia National Monument.

Road management
NOI in Federal Register
06/15/2007
DEIS NOA in Federal Register
01/30/2009
FEIS NOA in Federal Register
10/09/2009
Decision
12/2009 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
Chris Sanders · csanders@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityTravel Management
SEQUOIA NATIONAL FOREST MOTORIZED TRAVEL MANAGEMENTDecision Signed Date: 12/17/2009 Legal Notice Date: 12/28/2009
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District; Kern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 3/25/2016
Kernville Work Center · Kern, California

SUP for construction by Army Corps of Engineers for the USDA Forest Service Administration and Recreation Facilities Relocation

Special use management
Scoping Start
11/19/2015
Comment Period
11/19/2015
Decision
03/2016 (Estimated)
Implementation
09/2016 (Estimated)
Project documents
Roger Porter · rwporter@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
US ARMY CORPS OF ENGINEERS USDA FS ADMINISTRATION FACILITIES RELOCATION - CONSTRUCTION ACTIVITIESDecision Signed Date: 03/24/2016
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Sequoia National Forest All Units · updated 3/24/2016
Sequoia National Forest, portions of three districts · Fresno; Kern; Tulare, California

Proposal for over snow vehicle (OSV) road and facility maintenance program.

Recreation management
Scoping Start
12/09/2014
Decision
05/2016 (Estimated)
Implementation
11/2016 (Estimated)
Project documents
Karen Miller · kgmiller@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Maintenance
ForestsSequoia National Forest
DistrictsSequoia National Forest All Units
Legal Land DescriptionNot Applicable
Environmental Assessment · Kern River Ranger District · updated 3/8/2016
Project is accessed via Saddle Springs Road (27S02). · Kern, California

This is a shaded fuelbreak, around the Valley View community, that will be 250 feet long, with removal of snags, ladder fuels, and material on the ground.

Vegetation management (other than forest products)Fuels management
Scoping Start
01/13/2006
Objection Period Start
08/11/2010
Decision
11/2010 (Estimated)
Implementation
03/2011 (Estimated)
Project documents
Nickie Washington · nwashington@fs.fed.us
NEPA / regulatory detail
Special AuthorityHfra Title I: Wildland-Urban Interface
Notice and Comment Regulation218
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
Valley View Hazardous Fuels Reduction ProjectDecision Signed Date: 11/01/2010
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSection 33, T.27S., R.33E. and Section 3, T.28S., E.33E., MDM.
Decision Memo · Kern River Ranger District · updated 3/4/2016
The project is accessed via Highway 155 to Rancheria Road (25S15) south to Basket Pass Road (26S05). · Kern, California

This project is designed to reduce plantation conifer stocking levels and associated aerial fuels to improve plant vigor, increase resistance to insects, and reduce the risk of catastrophic wildfires.

Fuels managementVegetation management (other than forest products)
Scoping Start
10/13/2004
Decision
03/2005 (Estimated)
Implementation
07/2005 (Estimated)
Project documents
James Yearwood · jyearwood@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNational Fire Plan - Healthy Forests Initiative Ce
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
RED MOUNTAIN THINNING PAHSE 2Decision Signed Date: 03/21/2005
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT.26S., R.31 & 32E., MDM, and found within Greenhorn Ranger District Compartment Numbers 401 and 403.
Decision Memo · Kern River Ranger District · updated 3/3/2016
Within the Piute fire perimeter, specifically the subwatersheds of upper Thompson Canyon, Clear Creek, South Fork of Erskine Creek, upper Kelso Creek, and Woolstalf Creek · Kern, California

Planting by hand 2,824 acres; Mechanical site preparation & hand planting on additional 656 acres; Fell six trees per acre for wildlife cover adjacent to riparian areas over approx. 50 acres.

Vegetation management (other than forest products)Wildlife, fish, rare plants
Scoping Start
10/09/2009
Decision
03/2010 (Estimated)
Implementation
04/2010 (Estimated)
Project documents
Brian Bergman · brianbergman@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (11), 36 Cfr 220.6(E)(11)
Special AuthorityNational Fire Plan - Healthy Forests Initiative Ce
Notice and Comment RegulationNot Subject to Regulations
Project ActivityForest Vegetation Improvements; Species Habitat Improvements
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT28S, R34E, Sections 3-4,7-10,16-20, and 28-32; T28S, R33E, Sections 13, 22-27, and 35-36; T27S, R34E, Section 34; MDB&M
Decision Memo · Kern River Ranger District · updated 1/14/2016
The road (FS Road 28S37) is located near Breckenridge Lookout off of FS Road 28S07. · Kern, California

Re-issuing a Road SUP for a new 10-year term as the previous SUP holder sold property to Gary Costello. The only change to the previous permit is the Permit Holder.

Special use management
Scoping Start
10/11/2013
Comment Period
11/08/2013
Decision
12/2013 (Estimated)
Implementation
12/2013 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Decision Memo Breckenridge Lookout Road 10-Year Special Use PermitDecision Signed Date: 12/18/2013 (FS Withdrawn) Legal Notice Date: 12/21/2013
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSW1/4 Sec. 31, T.28S., R.32E., MDBM. This permit covers a right-of-way 1.1 mile in length, 12 feet in width, containing approximately 1.6 acres
Decision Memo · Kern River Ranger District · updated 11/30/2015
French, Mack, and/or Woolstalf Meadows · Kern, California

Piute Mountain meadow restoration project would improve conditions in three meadows burned during the Piute fire. These meadows include French, Mack, and Woolstaff.

Vegetation management (other than forest products)Watershed managementGrazing managementHeritage resource management
Scoping Start
09/07/2010
Decision
01/2012 (Estimated)
Implementation
05/2014 (Estimated)
Project documents
Keith Stone · kstone@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecies Habitat Improvements; Heritage Resource Management; Trail Management; Scenery Management; Watershed Improvements
Decision Memo Piute Mountains Meadows Restoration ProjectDecision Signed Date: 01/23/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT28S, R34E, MDB&M
Decision Memo · Kern River Ranger District · updated 10/22/2015
Southeast of Highway 155 and Northwest of the Greenhorn Summit. · Kern, California

Renewal of an existing water system that serves four recreation residence cabins.

Special use management
Scoping Start
07/24/2015
Decision
10/2015 (Estimated)
Implementation
10/2015 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
SLICKROCK WATER ASSOCIATION 20-YEAR SUP RE-ISSUANCEDecision Signed Date: 10/22/2015
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSection 20, T.25S., R.32E. MDBM
Decision Memo · Kern River Ranger District · updated 10/2/2015
North of Highway 155 and south and east of the Greenhorn Summit. · Kern, California

Special use permit renewal for water tank, water transmission line, and road access.

Special use management
Scoping Start
03/23/2015
Decision
05/2015 (Estimated)
Implementation
05/2015 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
DM for Alta Sierra Mutual Water Company 15-Year Special Use PermitDecision Signed Date: 05/19/2015
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSW1/4, Section 21, T.25S., R.32E. MDBM
Decision Memo · Kern River Ranger District · updated 9/23/2015
Off FS Road 21S02 near north end of Beach Meadow. · Tulare, California

Proposal to renew special use permit for unimproved dirt road (approximately 600 feet long and 12 feet wide for 0.16 acres) that accesses private property from FS Road 21S02 near Beach Meadow.

Special use management
Scoping Start
06/24/2015
Decision
09/2015 (Estimated)
Implementation
10/2015 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
TWOMBLY ROAD 20-YEAR SPECIAL USE PERMIT RE-ISSUANCEDecision Signed Date: 09/22/2015
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNE1/4, SW1/4, Section 3, T21S, R34E, MDB&M
Decision Memo · Sequoia National Forest All Units · updated 8/12/2015
One mile southeast of Alta Sierra, 45 miles east of Bakersfield, CA. It is within the lower Kern 5th order watershed, Tillie Creek watershed, and East Kern Air Pollution Control District · Kern, California

Salvage fire killed timber on 142 acres within the 2545 acre Shirley Fire area to reduce future fuel loading and provide for reforestation.

Forest productsFuels management
Scoping Start
10/01/2014
Decision
08/2015 (Estimated)
Implementation
08/2015 (Estimated)
Project documents
Brian Block · brianblock@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (5), 36 Cfr 220.6(E)(5); 32.2 (13), 36 Cfr 220.6(E)(13)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTimber Sales (Salvage)
Revised Shirley Fire Salvage and Forest Restoration ProjectDecision Signed Date: 08/12/2015
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionTownship 25 South, Range 32 East, sections 33 and 34; Township 26 South, Range 32 East, Section 4, Mount Diablo Base and Meridian
Decision Memo · Kern River Ranger District · updated 7/24/2015
Osa Meadow restoration project would be located off of Forest Service Road 20S25 on the Kern Plateau, located north of the Blackrock Work Center. Osa Meadow is approximately 90 acres in size. · Tulare, California

Meadow restoration project proposes to improve aquatic conditions and raise the water table beneath Osa Meadow.

Watershed management
Scoping Start
09/02/2010
Decision
07/2015 (Estimated)
Implementation
08/2016 (Estimated)
Project documents
Keith Stone · kstone@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (7), 36 Cfr 220.6(E)(7); 32.2 (18), 36 Cfr 220.6(E)(18)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityWatershed Improvements
Decision Memo, Osa Meadow Restoration ProjectDecision Signed Date: 07/24/2015
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSW 1/4 Section 16, SE 1/4 Section 17, T20S, R34E, MDB&M
Decision Memo · Kern River Ranger District · updated 6/10/2015
Kern Valley Airport, Kernville CA · Kern, California

Amends SUP to add approximately 295 feet of chain link fence (six foot high) to permitted area. Fencing is needed to meet FAA regulations for safety and security.

Special use management
Scoping Start
04/29/2014
Decision
06/2014 (Estimated)
Implementation
06/2014 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
KERN VALLEY AIRPORT FENCE LINE PROJECTDecision Signed Date: 06/05/2014
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSection 27, T25S, R33E, MDBM.
Decision Memo · Kern River Ranger District · updated 5/20/2015
North of Highway 155 and south and east of the Greenhorn Summit. · Kern, California

Renewal of the expired Sierra Bella Mutual Water Company special use permit for a 20-year term for water tanks, water transmission line, and access road with gate.

Special use management
Scoping Start
03/23/2015
Decision
05/2015 (Estimated)
Implementation
05/2015 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Sierra Bella Mutual Water Company 20-Year SUP Re-IssuanceDecision Signed Date: 05/19/2015
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSW1/4, Section 21, T.25S., R.32E. MDBM
Decision Memo · Kern River Ranger District · updated 1/13/2015
Kernville adjacent to Kern County Waste Disposal Transfer Station · Kern, California

Reissue 20 year special use permit for a target range. No changes are proposed. Current permit covers approximately 40 acres and 0.25 miles of road.

Special use management
Scoping Start
08/25/2014
Decision
01/2015 (Estimated)
Implementation
01/2015 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (10)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Kern River Valley Gun Association Target Range SUP (20 Year) Decision MemoDecision Signed Date: 01/13/2015
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNE1/4 Section 3, T26S, R33E, MDB&M
Decision Memo · Kern River Ranger District · updated 12/17/2014
Scodie Mountains, Kiavah Wilderness, Horse Canyon area · Kern, California

Install fencing to separate grazing management units and eliminate livestock access to riparian corridor.

Grazing management
Scoping Start
07/2013 (Estimated)
Decision
08/2013 (Estimated)
Implementation
08/2013 (Estimated)
Project documents
Steve Anderson · swanderson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (9), 36 Cfr 220.6(E)(9)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityGrazing Allotment Management
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSections 14 and 16, Township 27 South, Range 36 East, Mount Diablo Base and Meridian.
Decision Memo · Western Divide Ranger District · updated 10/1/2014
Road 20S92 (Bace Ranch Road) is located on the Western Divide RD of the Sequoia National Forest. It connects Tulare County Roads J37 from Mountain Home State Forest south to Tulare County Road 220. · Tulare, California

Proponent proposes to repair and maintain NFS Road No. 20S92, which includes resurfacing, cleaning culverts, road grading, and/or clearing the roadside of brush without the use of herbicides.

Special use management
Scoping Start
03/25/2014
Decision
10/2014 (Estimated)
Implementation
08/2014 (Estimated)
Project documents
ODell Tucker · otucker@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Decision Decided Date10/01/2014
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionSection 34, T19S, R30E, and Sections 3, 4 and 5, T20S, R30E, MDBM.
J & I APIARY SITES Completed
Decision Memo · Western Divide Ranger District · updated 9/30/2014
Permit covers 0.6 acre in N1/2 Section 22, T.22E.; and the W1/2 Section 18, T.23E., R.32E., Mount Diablo Base& Meridian. · Tulare, California

The decision will issue a 10-year apiary SUP for two sites (100 hives/site)and use of signs and electric bear fences.

Special use management
Scoping Start
02/24/2014
Decision
08/2014 (Estimated)
Implementation
09/2014 (Estimated)
Project documents
ODell Tucker · otucker@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
J&I APIARY SITES TEN YEAR SPECIAL USE PERMITDecision Signed Date: 08/06/2014
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionThe Pines Site: N1/2 Section 22, T.22S., R.32E. Speas Dirty Site: W1/2 Section 18, T.23S., R.32E
Decision Memo · Western Divide Ranger District · updated 9/30/2014
Spr 1&2: SW1/4, NW1/4, Section 3, T20S, R30E, MDBM; Spr 3: SE1/4, SW1/4, Section 34, T19S, R30E, MDBM; Spr 4: NW1/4, SW1/4, Section 3, T20S, R30E, MDBM; Spr 5: SW1/4, NW1/4, Section 3, T20S, R30E, MDB · Tulare, California

Water from four springs would be used to irrigate orchards located on the proponent's private property and water from one spring would be used to supply water to the proponent's house. The current water rights are for domestic and irrigation use.

Special use management
Scoping Start
03/25/2014
Decision
09/2014 (Estimated)
Implementation
10/2014 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (10)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Douglas McKee Water Systems 10-Year Special Use PermitDecision Signed Date: 09/08/2014
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Western Divide Ranger District · updated 7/10/2014
The project area is located 2.5 miles off Forest Service Road 21S05, at the end of Forest Service Trail 32E22. This area is east of Springville, along the Western Divide Highway. · Tulare, California

Proposed project to replace the lookout cab and tower with the same look and feel as the original tower on the same site. The lookout will comply with current building codes and safety requirements.

Facility management
Scoping Start
12/09/2011
Decision
04/2014 (Estimated)
Implementation
09/2014 (Estimated)
Project documents
Linn Gassaway · lgassaway@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (3), 36 Cfr 220.6(D)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFacility Improvements/Construction
Needles Lookout Decision MemoDecision Signed Date: 04/01/2014
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionTownship 21 South, Range 32 East, Section 14, MDBM
Decision Memo · Sequoia National Forest All Units · updated 6/30/2014
Kern River and Western Divide, non-wilderness areas · Kern; Tulare, California

Authorize issuance of two separate outfitter guide special use permits for guided hunting and fishing.

Special use managementRecreation management
Scoping Start
05/21/2014
Decision
06/2014 (Estimated)
Implementation
06/2014 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
MIKE BERRY & NEIL RAY HUNTING OUTFITTER GUIDE 10-YR SPECIAL USE PERMITSDecision Signed Date: 06/27/2014
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District; Kern River Ranger District
Legal Land DescriptionT19-29S, R30-35W, MDBM
BRUMLEY'S BEES Completed
Decision Memo · Kern River Ranger District · updated 6/26/2014
Various locations on the Kern River Ranger District · Kern; Tulare, California

Apiary Special Use Permit impacting less than five contiguous acres.

Special use management
Scoping Start
05/20/2014
Decision
06/2014 (Estimated)
Implementation
07/2014 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
BRUMLEY'S BEES APIARY SITE 10-YEAR SPECIAL USE PERMITSDecision Signed Date: 06/12/2014
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT20-29S, R33-35E, MDB&amp;M
Decision Memo · Hume Lake Ranger District · updated 6/26/2014
Davis Road (Forest Road 12S01) provides access between State Highway 180, and the Kings River above Pine Flat Reservoir. · Fresno, California

Proposal to maintain 11 miles of Davis Road (Forest Road No. 12S01) by replacing culverts, repairing the roadbed and other drainage features, and adding rock to the road surface.

Road management
Scoping Start
08/06/2010
Decision
05/2014 (Estimated)
Implementation
10/2014 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRoad Maintenance; Road Improvements/Construction; Travel Management; Watershed Improvements
Davis Road Maintenance ProjectDecision Signed Date: 05/29/2014
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT12-13S, R26-27E, MDB&M
Decision Memo · Kern River Ranger District · updated 5/21/2014
The project is located on the north side of Highway 155 and approximately 100 yards to the west of the entrance to Main Dam Campground. · Kern, California

Add two poles and lines to upgrade the SCE power line to the existing Isabella Lake hydroelectric plant.

Special use management
Scoping Start
03/31/2014
Decision
04/2014 (Estimated)
Implementation
06/2014 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNW 1 /4 Section 30, T26S, R33E
Decision Memo · Kern River Ranger District · updated 5/21/2014
Section 30, T28S, R32E, MDB&amp;M) approximately 200 feet south of Breckenridge Road No. 28S06. · Kern, California

Allow SCE to replace a damaged utility pole on Breckenridge.

Special use management
Scoping Start
03/31/2014
Decision
04/2014 (Estimated)
Implementation
05/2014 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
SCE DETERIORATED WOODEN POLE REPLACEMENT ON BRECKENRIDGE MTN POLE 4180731EDecision Signed Date: 04/25/2014
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNot Applicable
Decision Memo · Kern River Ranger District · updated 12/18/2013
The road is located to the west of Greenhorn Summit and south of Hwy. 155. · Kern, California

Re-issuing a Road SUP for a new 10-year term and installing a gate.

Special use management
Scoping Start
10/01/2013
Comment Period
11/02/2013
Decision
12/2013 (Estimated)
Implementation
01/2014 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Decision Memo Weeping Springs Road Association 10-year Special Use PermitDecision Signed Date: 12/09/2013 Legal Notice Date: 12/13/2013
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSec. 20, T. 25 S., R. 32 E., MDBM
Environmental Assessment · Hume Lake Ranger District · updated 9/27/2013
Hazardous or danger trees have been identified on portions of several district roads, mainly in Stony and Park Ridge areas. · Fresno; Tulare, California

Proposal to fell dead or damaged trees along district roads that pose a safety hazard or danger to public/employees using these routes. Some trees may be removed.

Road management
Scoping Start
06/29/2011
Comment Period
05/02/2013
Decision
09/2013 (Estimated)
Implementation
06/2014 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Maintenance
Hume Roadside and Recreation Site Hazard Tree ProjectDecision Signed Date: 09/26/2013 (Constrained Due to Litigation) Legal Notice Date: 09/27/2013
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13-15S, R28-29E
Decision Memo · Kern River Ranger District · updated 9/25/2013
Forestwide · Kern; Tulare, California

Proposal to continue operating supervised backpacking, hiking, and camping trips lasting from 1-2 weeks for 6th through 12th grade students.

Special use management
Scoping Start
09/2013 (Estimated)
Decision
10/2013 (Estimated)
Implementation
10/2013 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNE1/4, SW1/4, Section 3, T21S, R34E, MDBM
Environmental Assessment · Kern River Ranger District · updated 9/13/2013
Lower Kern Canyon and Greenhorn Mtns · Kern, California

Restore areas within Black Gulch North, Black Gulch South, and China Garden dispersed recreation areas in the Lower Kern Canyon. Protect sensitive resources in the vicinity of Evans Flat Campground located in the Greenhorn Mtns.

Road managementRecreation managementHeritage resource management
Scoping Start
10/26/2011
Comment Period
03/06/2013
Decision
09/2013 (Estimated)
Implementation
10/2013 (Estimated)
Project documents
Penelope Shibley · pshibley@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Developed Site Management; Dispersed Recreation Mgmt.; Travel Management
DN and FONSI Lower Kern Canyon and Greenhorn Mountains OHV Restoration ProjDecision Signed Date: 09/10/2013 Legal Notice Date: 09/13/2013
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionBlack Glch N: S 9-10, T27S, R32E;Black Glch S: S 10,15-16, T27S, R32E; China Grdn: S 33, T27S,R31E; Evans Flt: S 25,T26S,R32E; Kern Cyn Tr: S 3, T27S,R32E; Woodwd Pk Tr: S30, T26S,R32E
Environmental Assessment · Kern River Ranger District · updated 7/8/2013
Oak Ridge area, Greenhorn Mountains · Kern, California

An ecological restoration project in the Oak Ridge area of the Greenhorn Mountains. This project will implement sustainable forest practices by improving wildland fire safety, wildlife habitat, and economic use of forest by-products.

Forest products
Scoping Start
05/16/2011
Comment Period
04/23/2013
Decision
07/2013 (Estimated)
Implementation
11/2013 (Estimated)
Project documents
Penelope Shibley · pshibley@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green)
Rancheria Forest Restoration ProjectDecision Signed Date: 07/05/2013 Legal Notice Date: 07/05/2013
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT25 and 26S, R31 and 32E, MDBM
Environmental Assessment · Hume Lake Ranger District · updated 6/28/2013
Portion of Boulder drainage area west of Sheep Fire and north of Forest Road 14S02. · Fresno, California

Prescribe burn portions of Boulder Creek drainage in Monarch Wilderness and Agnew Roadless Area to continue reintroducing fire adjacent to the 2010 Sheep Fire. Fire would burn through a portion of Agnew, Deer Meadow, and Evans Complex Groves.

Special area managementFuels management
Scoping Start
03/29/2012
Comment Period
03/06/2013
Decision
04/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels)
Boulder Creek Fuels Restoration DN and FONSIDecision Signed Date: 04/22/2013 Legal Notice Date: 04/23/2013
Boulder Creek Fuels Restoration ProjectDecision Signed Date: 04/22/2013 Legal Notice Date: 04/23/2013
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13S, R29E, MDB&M
Decision Memo · Kern River Ranger District · updated 5/17/2013
French Gulch at Lake Isabella · Kern, California

Operation and maintenance of a Native American interpretive center (Forest Service building on Forest Service land)

Special use management
Scoping Start
03/29/2013
Comment Period
03/29/2013
Decision
05/2013 (Estimated)
Implementation
06/2013 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Kern River Paiute Council Nuui Cunni Cultural Center 5-Yr SUPDecision Signed Date: 05/14/2013 Legal Notice Date: 05/16/2013
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSection 19, T26S, R33E, MDB&M
Environmental Assessment · Western Divide Ranger District · updated 5/17/2013
Approximately 29 air miles east of Porterville, CA. · Tulare, California

Revision 1 to existing environmental documention to allow for forest thinning to reduce stand density for vegetation management, fuels management, and public safety activities.

Forest productsFuels management
Scoping Start
10/23/1998
Comment Period
04/14/2012
Decision
05/2013 (Estimated)
Implementation
07/2013 (Estimated)
Project documents
Richard Stevens · ristevens@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels); Timber Sales (Green)
Affirmation Existing Decision Dated 2/5/2001 Frog Project Area Analysis EADecision Signed Date: 05/14/2013 Legal Notice Date: 05/16/2013
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionT23-24S, R31-32E; MDB&M
Decision Memo · Kern River Ranger District · updated 5/17/2013
The road is located west of the Greenhorn Summit and south of Highway 178 in the Slick Rock Recreation Residence Tract. · Kern, California

Re-issue a road special use permit for a new 10-year term.

Special use management
Scoping Start
03/07/2013
Comment Period
03/07/2013
Decision
04/2013 (Estimated)
Implementation
05/2013 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Slick Rock Six Road Association 10-Year Special Use Permit DMDecision Signed Date: 04/12/2013 Legal Notice Date: 04/17/2013
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSec. 20, T.25S., R.32E., MDBM. The elevation of the road is approximately 6,000 feet above mean sea level (msl). The permit area is approximately 0.09 acres.
Decision Memo · Kern River Ranger District · updated 5/17/2013
The road is located to the south and adjacent to Jesse James Trailer Park off Tuttle Road. · Kern, California

This proposal is to issue a road SUP for a new 10-year term because the previous SUP Holder is deceased. There are no changes to the permitted area or use.

Special use management
Scoping Start
03/09/2013
Comment Period
03/09/2013
Decision
04/2013 (Estimated)
Implementation
05/2013 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Studebaker Road 10-Year Special Use Permit DMDecision Signed Date: 04/12/2013 Legal Notice Date: 04/17/2013
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land Description_SW1/4, Sec. 5, T26S, R33E, MDBM, The elevation of the road is approximately 2,600 feet above mean sea level (msl). The area for development is approximately 0.01 acres
Decision Memo · Kern River Ranger District · updated 4/25/2013
The water system is located in the Slick Rock Recreation Residence Tract west of the Greenhorn Summit and south of Highway 155. · Kern, California

Proposal to issue a water system special use permit for a new 10-year term.

Special use management
Scoping Start
03/07/2013
Comment Period
03/07/2013
Decision
04/2013 (Estimated)
Implementation
05/2013 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Buckhorn Water System Association 10-Year Special Use Permit DMDecision Signed Date: 04/12/2013 Legal Notice Date: 04/17/2013
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSec. 20, T.25S., R.32E., MDBM. The elevation of the water system is approximately 6,000 feet above mean sea level (msl). The permit area is approximately 0.01 acres.
Decision Memo · Kern River Ranger District · updated 4/9/2013
Boulder Gulch Campground · Kern, California

The project proposes to decommission approximately 6 miles of unauthorized routes and hill climbs leading away from the Boulder Gulch campground and day use area.

Vegetation management (other than forest products)Road managementRecreation management
Scoping Start
10/26/2011
Comment Period
02/06/2013
Decision
04/2013 (Estimated)
Implementation
04/2013 (Estimated)
Project documents
Penelope Shibley · pshibley@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (6), 36 Cfr 220.6(E)(6)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Developed Site Management; Dispersed Recreation Mgmt.; Travel Management
Boulder Gulch OHV Restoration Project Decision MemoDecision Signed Date: 04/01/2013 Legal Notice Date: 04/04/2013
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSections 7, 8, 17, 18, T26S, R33E, MDBM
Decision Memo · Kern River Ranger District · updated 4/5/2013
Various locations on the Kern River Ranger District · Kern; Tulare, California

Apiary special use permit, impacting less than five contiguous acres of National Forest System lands.

Special use management
Scoping Start
03/2013 (Estimated)
Decision
04/2013 (Estimated)
Implementation
04/2013 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Decision Memo · Kern River Ranger District · updated 3/29/2013
The waterline is located near Tillie Creek Campground. · Kern, California

Proposal to issue a new special use permit for a waterline to the new owner of the water company that services Jesse James Trailer Park.

Special use management
Scoping Start
01/26/2013
Comment Period
01/26/2013
Decision
03/2013 (Estimated)
Implementation
03/2013 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
CalWater Waterline 10-Year Special Use Permit Decision MemoDecision Signed Date: 03/28/2013
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSW ¼, Section 5, T.26S., R.33E. MDBM
Decision Memo · Kern River Ranger District · updated 2/1/2013
Near Big Meadow on the Kern River Ranger District of the Sequoia National Forest in Tulare County · Tulare, California

Renewal of special use permit for a cabin and road in conjunction with an existing grazing permit.

Special use management
Scoping Start
11/07/2011
Comment Period
11/07/2012
Decision
01/2013 (Estimated)
Implementation
01/2013 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Bruce Hafenfeld Range Use Facilities (Bldg & Rd) 10-Yr Special Use PermitDecision Signed Date: 01/28/2013 Legal Notice Date: 02/01/2013
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land Description1 acrea in NE ¼, Section 32, T23S, R34E, MDB&M
Decision Memo · Western Divide Ranger District · updated 12/27/2012
Near the community of Ponderosa, CA · Tulare, California

Proposal for a special use permit for an existing road accessing Ponderosa Community Services District's Holby Well water storage tanks.

Special use management
Scoping Start
05/12/2012
Comment Period
05/12/2012
Decision
12/2012 (Estimated)
Implementation
12/2012 (Estimated)
Project documents
Richard Stevens · ristevens@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Holby Well Access Road Special Use Permit Decision MemoDecision Signed Date: 12/20/2012 Legal Notice Date: 12/26/2012
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionSection 16, T21S, R32E, MDB&M
Decision Memo · Kern River Ranger District · updated 12/27/2012
The project area is located in the lower and upper Kern River Canyon. · Kern, California

Proposal for replacement of 19 deteriorated wood poles with light weight steel poles on the Borel-Isabella-KR3-Lakegen-Weldon and Borel-Havilah-Loraine-Monolith-Walker Basin 66kV transmission lines, Lower and Upper Kern River Canyon

Special use management
Scoping Start
10/03/2012
Comment Period
10/03/2012
Decision
11/2012 (Estimated)
Implementation
12/2012 (Estimated)
Project documents
Roger Porter · rwporter@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
SCE Replmt of 19 Deteriorated Wood Poles with Light Weight Steel Poles DMDecision Signed Date: 11/30/2012 Legal Notice Date: 12/22/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Decision Memo · Kern River Ranger District · updated 12/20/2012
Located on the west side of Lake Isabella. Occupies the same site as UNAVCO. · Kern, California

Proposal to renew SUP for earthquake sensing equipment and access road

Special use management
Scoping Start
09/05/2012
Comment Period
09/05/2012
Decision
10/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Decision Memo CalTech and UNAVCO Research Area and FLPMA Road EasementDecision Signed Date: 10/18/2012 Legal Notice Date: 10/24/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSE ¼, Section 18, T26S, R33E, MDB&M.
Decision Memo · Kern River Ranger District · updated 12/20/2012
Lake Isabella, Horse Canyon (Scodie Mountain), Landers Meadow (Piute Mountain), Rodeo Flat , Jackass Meadow, and Boone Meadow (Kern Plateau) · Kern, California

Proposal for a special use permit for survival training for the water and land-based air crew

Special use management
Scoping Start
08/18/2012
Comment Period
08/18/2012
Decision
10/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Edwards Air Force Base Pilot Survival Training (Land and Water) Special UseDecision Signed Date: 10/05/2012 Legal Notice Date: 10/11/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land Description.25 ac Sec 19, T26S, R33E; .75 ac Sec 17, T27S, R36E; .75 ac Sec 33 T28S, R34E; .75 ac Sec 20 T21S, R35E; .75 ac Sec 33, T21S, R35E; .75 ac Sec 20, T22S, R34E, MDB&M
Decision Memo · Kern River Ranger District · updated 12/20/2012
Western Divide and Kern River Ranger Districts · Kern; Tulare, California

Proposal for over snow vehicle (OSV) road and facility maintenance program

Recreation management
Scoping Start
08/22/2012
Comment Period
08/22/2012
Decision
10/2012 (Estimated)
Implementation
11/2012 (Estimated)
Project documents
Chris Sanders · csanders@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (4), 36 Cfr 220.6(D)(4); 32.12 (5), 36 Cfr 220.6(D)(5)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFacility Maintenance
2012-2013 OSV Maintenance and Grooming ActivitiesDecision Signed Date: 10/03/2012 Legal Notice Date: 10/11/2012
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District; Kern River Ranger District
Decision Memo · Kern River Ranger District · updated 12/20/2012
The waterline serves a ranch located near Havilah. · Kern, California

Proposal to issue a special use permit for an existing waterline for irrigation and domestic use to a new property owner.

Special use management
Scoping Start
10/03/2012
Comment Period
10/03/2012
Decision
11/2012 (Estimated)
Implementation
11/2012 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
DECISION MEMO TAMARA BARKLEY WATERLINE SPECIAL USE PERMITDecision Signed Date: 11/07/2012 Legal Notice Date: 11/07/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNE ¼, Section 10, T28S, R32E, MDBM
Decision Memo · Kern River Ranger District · updated 12/20/2012
Located on the west side of Lake Isabella. Occupies same site as CalTech. · Kern, California

Proposal to renew existing SUP for earthquake sensing equipment and an access road.

Special use management
Scoping Start
09/05/2012
Comment Period
09/05/2012
Decision
10/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Decision Memo CalTech and UNAVCO Research Area and FLPMA Road EasementDecision Signed Date: 10/18/2012 Legal Notice Date: 10/24/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSE ¼, Section 18, T26S, R33E, MDBM.
Decision Memo · Kern River Ranger District · updated 9/27/2012
Riverkern, in Tulare and Kern Counties CA · Kern; Tulare, California

SCE proposes to obtain geologic information about the existing roadway in support of design and engineering for future road improvements.

Special use management
Scoping Start
05/24/2012
Comment Period
05/24/2012
Decision
07/2012 (Estimated)
Implementation
07/2012 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (8), 36 Cfr 220.6(E)(8)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Decision Memo SCE Kern River No.3 (#2290) Forebay Road Geotechnical InvestDecision Signed Date: 07/03/2012 Legal Notice Date: 07/10/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionKernville USGS quad, Sections 3 & 4, T25S, R33E
Decision Memo · Kern River Ranger District · updated 9/27/2012
Alta Sierra area · Kern, California

Re-issue special use permit SUP for existing nontoxic liquid waste disposal site. Includes a septic tank (8 ft X 6 ft) and a leach line (50 ft X 1 ft), for approximately .01 acres. SUP to be issued for 5 years. Formerly the Jack McGee sewer system.

Special use management
Scoping Start
04/24/2009
Decision
08/2012 (Estimated)
Implementation
08/2012 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Decision Memo Jim Thomsen Liquid Waste Disposal Site (Septic System) SUPDecision Signed Date: 08/27/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSW1/4 Section 21, T25S, R32E, MDB&M. Approximately .01 acres.
Decision Memo · Kern River Ranger District · updated 9/19/2012
Wofford Heights near Tillie Creek Campground · Kern, California

Proposal for maintenance and operation of 475-foot water transmission line (less than 12 inches diameter) covering 0.03 acres

Special use management
Scoping Start
07/2012 (Estimated)
Decision
08/2012 (Estimated)
Implementation
08/2012 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionSection 5, T26S, R33E; MDB&M
Environmental Assessment · Hume Lake Ranger District · updated 8/7/2012
Pine Ridge east to Davis Road (FR12S01). · Fresno, California

Proposal is to reduce fuel buildup around young plantation trees & continue reestablishing a more natural fire return interval through prescribed burning and mastication on portion of Pine Ridge area affected by 2001 Highway Fire.

Recreation managementVegetation management (other than forest products)Fuels management
Scoping Start
04/30/2010
Comment Period
04/20/2012
Decision
08/2012 (Estimated)
Implementation
10/2012 (Estimated)
Project documents
Paul Leusch · pleusch@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements
Pine Ridge Fuel Reduction ProjectDecision Signed Date: 08/03/2012 Legal Notice Date: 08/04/2012
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionT13S, R28E, MDB&M
Environmental Impact Statement · WO - Washington Office - National headquarters · updated 7/10/2012
11 contiguous Western States (Arizona, California, Colorado, Idaho, Montana, New Mexico, Nevada, Oregon, Utah, Washington, and Wyoming) and Alaska. · Bonner; Aleutians East; La Paz; Columbia; Coos; Colusa; Denver; Douglas, Alaska; Arizona; California; Colorado; District of Columbia; Idaho; Kansas; Montana; North Dakota; Nebraska; New Mexico; Nevada; Oklahoma; Oregon; South Dakota; Texas; Utah; Washington; Wyoming

The Forest Service was a cooperating agency, assisting the Bureau of Land Management (BLM) in that Agency's geothermal leasing analysis and decision. The BLM issued a record of decision on 12/17/2008.

Regulations, directives, orders
NOI in Federal Register
06/13/2007
DEIS NOA in Federal Register
06/13/2008
FEIS NOA in Federal Register
10/24/2008
Decision
02/2010 (Estimated)
Implementation
03/2010 (Estimated)
Project documents
Tracy Parker · tparker03@fs.fed.us
NEPA / regulatory detail
Special AuthorityNepa Document Prepared By Another Federal Agency
Notice and Comment RegulationNot Subject to Regulations
Project ActivityRegulation Creation/Modification
ForestsBeaverhead-Deerlodge National Forest; Bitterroot National Forest; Clearwater National Forest; Custer National Forest; Custer Gallatin National Forest; Helena National Forest; Lewis And Clark National Forest; Lolo National Forest; Nez Perce-Clearwater National Forest; Grand Mesa, Uncompahgre and Gunnison National Forests; Medicine Bow-Routt National Forest; Rio Grande National Forest; Arapaho and Roosevelt National Forests; Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands; San Juan National Forest; White River National Forest; Apache-Sitgreaves National Forests; Carson National Forest; Cibola National Forest; Coronado National Forest; Gila National Forest; Lincoln National Forest; Santa Fe National Forest; Tonto National Forest; Boise National Forest; Bridger-Teton National Forest; Dixie National Forest; Fishlake National Forest; Manti-Lasal National Forest; Payette National Forest; Salmon-Challis National Forest; Sawtooth National Forest; Caribou-Targhee National Forest; Humboldt-Toiyabe National Forest; Uinta-Wasatch-Cache National Forest; Angeles National Forest; Cleveland National Forest; Eldorado National Forest; Inyo National Forest; Klamath National Forest; Lassen National Forest; Los Padres National Forest; Mendocino National Forest; Modoc National Forest; Plumas National Forest; San Bernardino National Forest; Sequoia National Forest; Shasta Trinity National Forest; Sierra National Forest; Tahoe National Forest; Deschutes National Forest; Fremont-Winema National Forest; Gifford Pinchot National Forest; Malheur National Forest; Mt Baker-Snoqualmie National Forest; Mt. Hood National Forest; Ochoco National Forest; Rogue River-Siskiyou National Forest; Umatilla National Forest; Umpqua National Forest; Wallowa-Whitman National Forest; Okanogan-Wenatchee National Forest; Willamette National Forest; R10 - Alaska Region All Units; WO - Washington Office - National headquarters
DistrictsBeaverhead-Deerlodge National Forest All Units; Bitterroot National Forest All Units; Clearwater National Forest All Units; Custer National Forest All Units; Custer Gallatin National Forest; Custer Gallatin National Forest All Units; Helena National Forest All Units; Lewis And Clark National Forest All Units; Lolo National Forest All Units; Nez Perce-Clearwater National Forest All Units; Grand Mesa Uncompahgre and Gunnison National Forest All Units; Medicine Bow-Routt National Forest All Units; Rio Grande National Forest All Units; Arapaho and Roosevelt National Forests All Units; Pike and San Isabel National Forests and Cimarron and Comanche National Grasslands All Units; San Juan National Forest All Units; White River National Forest All Units; Apache-Sitgreaves National Forests All Units; Carson National Forest All Units; Cibola National Forest All Units; Coronado National Forest All Units; Gila National Forest All Units; Lincoln National Forest All Units; Santa Fe National Forest All Units; Tonto National Forest All Units; Boise National Forest All Units; Bridger-Teton National Forest All Units; Dixie National Forest All Units; Fishlake National Forest All Units; Manti-La Sal National Forest All Units; Payette National Forest All Units; Salmon-Challis National Forest All Units; Sawtooth National Forest All Units; Caribou-Targhee National Forest All Units; Humboldt-Toiyabe National Forest All Units; Uinta-Wasatch-Cache All Units; Angeles National Forest All Units; Cleveland National Forest All Units; Eldorado National Forest All Units; Inyo National Forest All Units; Klamath National Forest All Units; Lassen National Forest All Units; Los Padres National Forest All Units; Mendocino National Forest All Units; Modoc National Forest All Units; Plumas National Forest All Units; San Bernardino National Forest All Units; Sequoia National Forest All Units; Shasta Trinity National Forest All Units; Sierra National Forest All Units; Tahoe National Forest All Units; Deschutes National Forest All Units; Fremont-Winema National Forest All Units; Gifford Pinchot National Forest All Units; Malheur National Forest All Units; Mt Baker-Snoqualmie National Forest All Units; Mt. Hood National Forest All Units; Ochoco National Forest All Units; Rogue River-Siskiyou National Forest All Units; Umatilla National Forest All Units; Umpqua National Forest All Units; Wallowa-Whitman National Forest All Units; Okanogan-Wenatchee National Forest All Units; Willamette National Forest All Units; R10 - Alaska Region All Units; WO - Washington Office - National headquarters
Decision Memo · Kern River Ranger District · updated 6/28/2012
Southeastern Tulare County and northeastern Kern County and extends from the community of Johnsondale, south along Kern River Highway to Riverkern and the Kernville yydroelectric substation. · Kern; Tulare, California

Electric system improvements for grid reliability and maintenance at 33 stations on the Seequoia National Forest.

Special use management
Scoping Start
04/17/2012
Comment Period
04/17/2012
Decision
05/2012 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
Southern California Edison Grid Reliability/Intake 16kV Cutover ProjectDecision Signed Date: 05/23/2012 Legal Notice Date: 05/29/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Decision Memo · Kern River Ranger District · updated 5/24/2012
The proposed project is located off of Breckenridge Lookout road within the KBAK TV transmitting facility located northeast of Bakersfield on lands administered by Sequoia National Forest. · Kern, California

Communications site facility improvements including a new power pole interset between two existing poles; new power equipment on the side of existing building; and overhead work at two adjoining poles.

Special use management
Scoping Start
04/17/2012
Comment Period
04/17/2012
Decision
05/2012 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
Penelope Shibley · pshibley@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2); 32.2 (3), 36 Cfr 220.6(E)(3)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivitySpecial Use Authorizations
SCE Grid Reliability and Maintence/Breckenridge Interset PoleDecision Signed Date: 05/23/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT28S, R31E, Section 36, NE 1/4
Decision Memo · Kern River Ranger District · updated 5/24/2012
Project is located in southeastern Tulare County and northeastern Kern County, extends from the community of Johnsondale south along Kern River Highway to Riverkern and Kernville Hydro Substation. · Kern; Tulare, California

Southern California Edison (SCE) proposes the removal of wire and replacement of overhead transformers; pole removal and replacement; installation of new poles, anchors, and replacement of downguys. The project entails a 16kV to 12kV cutover.

Special use management
Scoping Start
04/17/2012
Comment Period
04/17/2012
Decision
05/2012 (Estimated)
Implementation
05/2012 (Estimated)
Project documents
Penelope Shibley · pshibley@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (2), 36 Cfr 220.6(E)(2)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityBoundary Adjustments
SCE Grid Reliability/Intake 16kV Cutover ProjectDecision Signed Date: 05/23/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT22-25S, R32-33E, MDB&M
Decision Memo · Kern River Ranger District · updated 3/27/2012
Isabella Lake · Kern, California

Issue a Special Use Permit for annual fishing derbies on Isabella Lake for a 5-year term. The annual derby takes place over a 3-day period.

Special use management
Scoping Start
10/15/2011
Decision
02/2012 (Estimated)
Implementation
03/2012 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (15)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivitySpecial Use Authorizations
Kern River Valley Chamber of Commerce Annual Fishing DerbyDecision Signed Date: 02/14/2012
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT 25-26S, R 33-34 E, MDBM
Decision Memo · Western Divide Ranger District · updated 1/23/2012
Trail of 100 Giants (Forest Service Trail 31E00) east of Springville, along the Western Divide Highway, approximately three air miles west of the community of Johnsondale, Tulare County, CA. · Tulare, California

The project proposes to build a boardwalk, meeting ADA requirements, that connects the trail from the remaining northern-most bridge on the south side of the fallen sequoias, to the existing trail on the east-side.

Recreation management
Scoping Start
12/09/2011
Decision
01/2012 (Estimated)
Implementation
04/2012 (Estimated)
Project documents
Marianne Thomas · mariannethomas@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (1), 36 Cfr 220.6(E)(1)
Special AuthorityNot Applicable / Other
Notice and Comment RegulationNot Subject to Regulations
Project ActivityTrail Management
Fallen Giants at Trail of 100 Giants ProjectDecision Signed Date: 01/20/2012
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionTownship 22 South, Range 31 East, Section 35, MDBM
Environmental Assessment · Sequoia National Forest All Units · updated 10/19/2010
The Coy Flat Tract adjoins the town of Camp Nelson, CA. Tract has 41 residences; lots averaging approximately 1/2 acre each. No Giant Sequoia. N1/2, Sec. 3, T.21.S., R.31E., MDM. · Tulare, California

The Slate Mountain Homeowners Association proposes to exchange three (3) privately held parcels (non-federal) inside the boundaries of the Giant Sequoia National Monument (GSNM) for federal land of equal value located inside the GSNM boundary.

Land ownership managementFacility management
Scoping Start
03/14/2008
Comment Period
05/28/2009
Decision
07/2009 (Estimated)
Implementation
08/2009 (Estimated)
Project documents
Roger Porter · rwporter@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.12 (7), 36 Cfr 220.6(D)(7)
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityBoundary Adjustments; Land Exchanges
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionBlack Mountain, 74.13 ac, Sec. 9, T.21S., R.31E., MDM; Freeman, 10 ac, Sec. 33, T.20S., R32E., MDM; & Wheel Meadow, 14.67 ac, Sec. 7 & 8, T.21S., R.32E., MDM.
Environmental Assessment · Hume Lake Ranger District · updated 10/19/2010
At Bearskin Diabetic Youth Camp, off of Forest Road 13S09 (Tenmile Road). · Fresno, California

Renovation of camp infrastructure: bathroom facilities, septic system, medical headquarters, sleeping decks, staff accommodations, and dining hall, to meet current health and safety standards and to better serve the youth and family.

Recreation managementSpecial use management
Scoping Start
12/04/2006
Comment Period
02/18/2009
Decision
12/2009 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDeveloped Site Management; Special Use Authorizations
BEARSKIN DIABETIC YOUTH CAMP RENOVATION PROJECTDecision Signed Date: 12/01/2009 Legal Notice Date: 12/04/2009
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionSec. 26, T.13S., R.28E., MDM. Approximately 5 acres.
Environmental Assessment · Kern River Ranger District · updated 10/19/2010
The route for the water transmission line begins at the Sequoia National Forest boundary northwest from Highway 155 and Old State Road, and ends at the Forest boundary and Old State Road. · Kern, California

A 30-year term special use permit, to install an underground water transmission line along-side and underneath the existing Old State Road. The trench will be approximately 900 feet long, 24 inches wide, and 42 inches deep.

Special use management
Scoping Start
04/18/2008
Comment Period
02/27/2009
Decision
04/2009 (Estimated)
Implementation
05/2009 (Estimated)
Project documents
Art Colson · acolson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityHarzardous Waste Compliance Actions; Special Use Authorizations
LIVE OAK WATERLINE INSTALLATION PROJECTDecision Signed Date: 04/23/2009 Legal Notice Date: 04/28/2009
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionNW 1/4 NW 1/4 NE 1/4 NW 1/4 Section 5, T.26S., R.33E., MDM. (as shown on the USGS Lake Isabella North, California, 7/5" series topographic map).
Environmental Assessment · Hume Lake Ranger District · updated 10/19/2010
Reconstruction and construction would occur within and adjacent to the approximately 42 acre authorized special use permit area. · Fresno, California

Upgrading and renovating facilities and infrastructure of resort complex, includes reconstruction and construction of several buildings.

Facility managementSpecial use managementRecreation management
Scoping Start
09/24/2007
Comment Period
02/18/2009
Decision
12/2009 (Estimated)
Implementation
05/2010 (Estimated)
Project documents
Marianne Emmendorfer · mmemmendorfer@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityDeveloped Site Management; Special Use Authorizations; Facility Maintenance
MONTECITO LAKE RESORT EXPANSION PROJECTDecision Signed Date: 12/01/2009 Legal Notice Date: 12/04/2009
ForestsSequoia National Forest
DistrictsHume Lake Ranger District
Legal Land DescriptionSec. 19, R.14S., R.29E., MDM.
Environmental Assessment · Western Divide Ranger District · updated 10/19/2010
The project is located on the Western Divide Ranger District, adjacent to the community of California Hot Springs, CA. · Tulare, California

Renewal of special use authorizations permitting grazing on two (2) allotments.

Grazing management
Scoping Start
06/27/2007
Comment Period
08/08/2009
Decision
09/2009 (Estimated)
Implementation
10/2009 (Estimated)
Project documents
Joe Loehner · jloehner@fs.fed.us
NEPA / regulatory detail
Categorical ExclusionSec 339
Special AuthorityGrazing, Rescissions Act Of 1995
Notice and Comment Regulation215
Project ActivityGrazing Authorizations
RUBE & POWDER MAGAZINE GRAZING PROJECTDecision Signed Date: 09/18/2009 Legal Notice Date: 09/18/2009
ForestsSequoia National Forest
DistrictsWestern Divide Ranger District
Legal Land DescriptionT.22-23S., R.30-31E., MDM. Location from California Hot Springs, CA, is approximately 5 miles to the north, 2 miles to the east, and 4 miles to the west.
Environmental Assessment · Kern River Ranger District · updated 9/18/2008
Greenhorn Mountain range along the ridgeline from the Rhymes Camp area to Davis. Rancheria Road bisects the project area. · Kern, California

Mechanical and manual treatments to reduce stand densities and surface and ladder fuels in forest stands and plantations to improve forest stand health, vigor, and resistance to fire, disease, and climate change.

Fuels managementForest productsVegetation management (other than forest products)
Scoping Start
07/2008 (Estimated)
Comment Period
08/2008 (Estimated)
Decision
09/2008 (Estimated)
Implementation
09/2008 (Estimated)
Project documents
Susan Porter · smporter@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Timber Sales (Green)
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionT.25, 26 & 27S., R.31 & 32E., MDM. Approximately 3,500 acres.
Environmental Impact Statement · R5 - Pacific Southwest Region All Units · updated 12/28/2007
Along Sierra Nevada chain from Oregon/California border to south of Lake Isabella as well as lands in western Nevada · Douglas; Esmeralda; Mineral; Alpine; Amador; Butte; Calaveras; El Dorado; Fresno; Inyo; Kern; Lassen; Madera; Mariposa; Modoc; Mono; Nevada; Placer; Plumas; Shasta; Sierra; Siskiyou; Tulare; Tuolumne; Yuba, California; Nevada

Amend Land and Resource Management Plans for ten (10) Forests within the Sierra Nevada region by modifying Management Indicator Species (MIS) lists and associated monitoring strategies.

Wildlife, fish, rare plantsLand management planning
NOI in Federal Register
04/30/2007
DEIS NOA in Federal Register
07/13/2007
FEIS NOA in Federal Register
12/28/2007
Decision
12/2007 (Estimated)
Implementation
01/2008 (Estimated)
Project documents
Diana Craig · dcraig01@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation219 (1982)
Project ActivityPlan Amendment
Sierra Nevada Forests Management Indicator Species AmendmentDecision Signed Date: 12/14/2007 Legal Notice Date: 12/21/2007
ForestsEldorado National Forest; Inyo National Forest; Lassen National Forest; Modoc National Forest; Plumas National Forest; Sequoia National Forest; Sierra National Forest; Stanislaus National Forest; Tahoe National Forest; Lake Tahoe Basin Mgt Unit
DistrictsEldorado National Forest All Units; Inyo National Forest All Units; Lassen National Forest All Units; Modoc National Forest All Units; Plumas National Forest All Units; Sequoia National Forest All Units; Sierra National Forest All Units; Stanislaus National Forest All Units; Tahoe National Forest All Units; Lake Tahoe Basin Mgt Unit
Decision Memo · Kern River Ranger District · updated 12/16/2004
Kern Plateau area on the Cannell Meadow Ranger District. · Kern; Tulare, California

Fuels management project on the Kern Plateau - Strategically Placed Area Treatment (SPLAT).

Fuels management
Scoping Start
05/01/2004
Decision
11/2004 (Estimated)
Implementation
11/2004 (Estimated)
Project documents
James Yearwood · jyearwood@fs.fed.us
NEPA / regulatory detail
Categorical Exclusion32.2 (10)
Special AuthorityNational Fire Plan - Healthy Forests Initiative Ce
Notice and Comment RegulationNot Subject to Regulations
Project ActivityFuel Treatments (Non-Activity Fuels)
ForestsSequoia National Forest
DistrictsKern River Ranger District
Legal Land DescriptionDistrictwide. Westside of Kern Plateau. 18,000 acres.
Environmental Impact Statement · Sequoia National Forest All Units · updated 8/9/2004
Area burned in the McNally Fire on the Kern Plateau, Cannell Meadow Ranger District, outside of roadless areas. · Fresno; Kern; Tulare, California

Restoration and timber salvage in burned area.

Wildlife, fish, rare plantsFuels managementVegetation management (other than forest products)Watershed managementForest products
NOI in Federal Register
01/03/2003
DEIS NOA in Federal Register
11/28/2003
FEIS NOA in Federal Register
03/25/2004
Decision
03/2004 (Estimated)
Implementation
07/2004 (Estimated)
Project documents
Thomas Simonson · tsimonson@fs.fed.us
NEPA / regulatory detail
Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityFuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Timber Sales (Salvage); Watershed Improvements
MCNALLEY-SHERMAN PASS RESTORATIONDecision Signed Date: 03/25/2004 Legal Notice Date: 03/27/2004
ForestsSequoia National Forest
DistrictsSequoia National Forest All Units
Legal Land DescriptionForestwide. T.21, 22, 23S., R.33, 34, 35E., MDM.