Reconstruct & construct buildings and other infrastructure such as waterlines within the permitted areas for both Stony Creek and Montecito Lake resorts to improve function and visitor services.
Location
Both resorts are on General's Highway between the junction with Forest Road 14S11 and the Sequoia National Park boundary to the southeast.
Project timeline
1
Scoping Start
06/24/2019
2
Comment Period
05/15/2020
3
Decision
07/2020 (Estimated)
4
Implementation
08/2020 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Developed Site Management; Special Use Authorizations; Facility Maintenance |
| MONTECITO LAKE AND STONY CREEK RESORTS UPGRADES | Decision Signed Date: 07/07/2020 |
| Forests | Sequoia National Forest |
| Districts | Hume Lake Ranger District |
| Legal Land Description | T14S, R29E, Sec. 19 (Montecito) and 32 (Stony) |