This project will consider decommissioning several roads/segments in the Black Mtn giant sequoia grove
Location
Spur Roads No. 21S12B, 21S25A, 21S25B, 21S25C, 21S25D and Road No. 21S25 east from its intersection with 21S25B.
Project timeline
1
Scoping Start
10/2017 (Estimated)
2
Comment Period
11/2017 (Estimated)
3
Objection Period Start
01/2018 (Estimated)
4
Decision
02/2018 (Estimated)
5
Implementation
06/2018 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Travel Management; Watershed Improvements |
| Forests | Sequoia National Forest |
| Districts | Western Divide Ranger District |
| Legal Land Description | T21S, R31E, Sections 1, 7, 12 |