Treat up to 6,700 acres through thinning, sanitation, mastication and prescribed burn to improve forest health and wildlife habitat, and reduce fuels in Tenmile Creek drainage.
Location
The project is located between state highway 180 and Forest Road 14S02 (Burton Pass Road).
Project timeline
1
Scoping Start
09/21/2021
2
Comment Period
03/16/2023
3
Objection Period Start
06/01/2023
4
Decision
12/2023 (Estimated)
5
Implementation
03/2024 (Estimated)
NEPA / regulatory detail
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 218 (2013) Non-HFRA |
| Project Activity | Road Decommissioning; Fuel Treatments (Non-Activity Fuels); Forest Vegetation Improvements; Species Habitat Improvements; Road Maintenance; Timber Sales (Salvage); Timber Sales (Green) |
| Hume Basin Restoration | Decision Signed Date: 12/04/2023 |
| Forests | Sequoia National Forest |
| Districts | Hume Lake Ranger District |
| Legal Land Description | T13-14S, R28E, MDB&M |