The project proposes to decommission approximately 6 miles of unauthorized routes and hill climbs leading away from the Boulder Gulch campground and day use area.
Location
Boulder Gulch Campground
Project timeline
1
Scoping Start
10/26/2011
2
Comment Period
02/06/2013
3
Decision
04/2013 (Estimated)
4
Implementation
04/2013 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (6), 36 Cfr 220.6(E)(6) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Road Decommissioning; Developed Site Management; Dispersed Recreation Mgmt.; Travel Management |
| Boulder Gulch OHV Restoration Project Decision Memo | Decision Signed Date: 04/01/2013 Legal Notice Date: 04/04/2013 |
| Forests | Sequoia National Forest |
| Districts | Kern River Ranger District |
| Legal Land Description | Sections 7, 8, 17, 18, T26S, R33E, MDBM |