Project timeline
1
Scoping Start
03/23/2015
2
Decision
05/2015 (Estimated)
3
Implementation
05/2015 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| DM for Alta Sierra Mutual Water Company 15-Year Special Use Permit | Decision Signed Date: 05/19/2015 |
| Forests | Sequoia National Forest |
| Districts | Kern River Ranger District |