Environmental Assessment Completed

Westside Plantation Project

Shasta-Trinity National Forest Trinity, California Shasta Trinity National Forest All Units

Thinning of overstocked plantations to improve vigor and reduce hazardous fuels on the west side of the Shasta-Trinity National Forest.

Location

Middle South Fork Trinity River Watershed

Project timeline

1
Scoping Start
09/24/2008
2
Comment Period
08/06/2014
3
Objection Period Start
10/02/2014
4
Decision
02/2015 (Estimated)
5
Implementation
03/2016 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation218 (2013) Non-HFRA
Project ActivityFuel Treatments (Non-Activity Fuels)
Westside Plantation Project Decision NoticeDecision Signed Date: 02/19/2015
ForestsShasta Trinity National Forest
DistrictsYolla Bolla Ranger District; Hayfork Ranger District
Legal Land DescriptionVarious sections within T10N - T26N, R6N - R6E
Fuels managementVegetation management (other than forest products)