Authorize sampling of lode deposits by excavation of horizontal tunnel into bedrock (mining adit) and processing of ore on the Braden Mine Lode #2. Amount of processed ore < or = 200 cubic yards. Total area of disturbance < or = 1 acre.
Location
On Carrier Gulch road 0.3 miles west of Wildwood Road & approx 5 air miles SE of Hayfork, CA.
Project timeline
1
Scoping Start
11/10/2010
2
Decision
07/2011 (Estimated)
3
Implementation
09/2011 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (8), 36 Cfr 220.6(E)(8) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Minerals Or Geology Plans Of Operations |
| Forests | Shasta Trinity National Forest |
| Districts | Hayfork Ranger District |
| Legal Land Description | T 31N, R11W, S 27 Mount Diablo Meridian |