Project timeline

1
Scoping Start
12/30/2011
2
Comment Period
02/2016 (Estimated)
3
Decision
03/2017 (Estimated)
4
Implementation
08/2017 (Estimated)

NEPA / regulatory detail

Special AuthorityNot Applicable / Other
Notice and Comment Regulation215
Project ActivityRoad Decommissioning; Road Maintenance; Watershed Improvements
ForestsShasta Trinity National Forest
DistrictsBig Bar Ranger District
Legal Land DescriptionThe watershed is located in T.34N., R.11W., sections 21-29 and 32-36; T.33N., R.11W., sections 1-5, 8-17, 21-28 and 33-36; T.32N., R.11W., sections 1-4, 10-12 and 14; T.33N., R.10W., sections 18, 19 a
Watershed management