Wintun Development Corporation has requested reauthorization of approximately 525 feet of buried powerline that serves the two street lights located at the intersection of the Ski Park Highway and Highway 89.
Location
At the intersection of the Ski Park Highway and Highway 89 at the summit of Snowman's Hill
Project timeline
1
Scoping Start
08/08/2012
2
Comment Period
08/08/2012
3
Decision
09/2012 (Estimated)
4
Implementation
09/2012 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (15) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | 215 |
| Project Activity | Special Use Authorizations |
| Mt. Shasta Board and Ski Park Powerline Special Use Permit Reauthorization | Decision Signed Date: 09/10/2012 Legal Notice Date: 09/13/2012 |
| Forests | Shasta Trinity National Forest |
| Districts | Mt. Shasta Ranger District |
| Legal Land Description | Section 32, T.40N., R.3W., M.D.B.M. |