Upgrade existing communications equipment to 4G capability and issue a new authorization to replace existing authorization.
Location
Township 33 North, Range 4 West, Section 7 MDM
Project timeline
1
Scoping Start
10/09/2015
2
Decision
06/2018 (Estimated)
3
Implementation
07/2018 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations |
| Ubiquitel Bass Mountain Communication Site Upgrade | Decision Signed Date: 06/28/2018 |
| Forests | Shasta Trinity National Forest |
| Districts | Shasta Lake Ranger District |
| Legal Land Description | Not Applicable |