The UM Shasta Camp has requested to amend their special use permit to add a solar array. The Camp operates off the grid and is working towards a more sustainable energy option to reduce their dependence on propane. INFORMAL SCOPING.
Location
UM Shasta Camp - Organization Camp
Project timeline
1
Scoping Start
06/15/2016
2
Decision
10/2016 (Estimated)
3
Implementation
11/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Not Applicable / Other |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Solar |
| UM Shasta Camp Permit Amendment to add Solar Array | Decision Signed Date: 10/21/2016 |
| Forests | Shasta Trinity National Forest |
| Districts | Mt. Shasta Ranger District |
| Legal Land Description | T39N, R5W, Section 13, Mount Diablo Basin Meridian |