New temporary road construction (~900 feet) is proposed at the west edge of the West Girard Inventoried Roadless Area. Some brush and conifer tree removal is proposed, as is closure and rehabilitation when the harvest unit is complete.
Location
Five miles east of Pollard Flat, CA.
Project timeline
1
Scoping Start
11/24/2015
2
Decision
02/2016 (Estimated)
3
Implementation
03/2016 (Estimated)
NEPA / regulatory detail
| Categorical Exclusion | 32.2 (3), 36 Cfr 220.6(E)(3) |
| Special Authority | Ira - Inventoried Roadless Area Activities Requiring Chief's Approval |
| Notice and Comment Regulation | Not Subject to Regulations |
| Project Activity | Special Use Authorizations; Road Improvements/Construction |
| North Salt Creek Temporary Road Request Project | Decision Signed Date: 02/22/2016 |
| Forests | Shasta Trinity National Forest |
| Districts | Mt. Shasta Ranger District |
| Legal Land Description | T35N R3W S10 SE 1/4 SE 1/4 M.D.B.M. |